The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
Federal services to slowly recover following end of government shutdown
IL congressman pushes military to accept CLT, experts say it could shape education
New Lenox Solar Farm Gains County Committee Approval with Conditions
Committee Approves Frankfort Township Gaming Bar on Split Vote
Crete Township Senior Group Home Gets Unanimous Committee Support
Beecher-Area Rezoning and Variances Approved to Legalize Structure
Committee Approves Wilton Township Land Division Despite Spot Zoning Concerns
MS-13 members prosecuted nationwide for brutal murders, fentanyl trafficking
Illinois, Chicago residents rank high taxes as state’s top issue
Jan. 6 panel cost twice previous estimates, hiring TV producers to dramatize attack
Illinois quick hits: Illinois House members vote along party lines; More than 40% of CPS teachers missed 10 or more school days; State Treasurer says Bright Start earns gold
Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for November 4, 2025