Screenshot-2025-08-13-at-2.15.28-PM

Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Spread the love

Article Summary:

The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.

Public Works Building Key Points:

  • Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.

  • The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.

  • Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.

MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.

Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.

Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”

With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.

“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”

The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.

Leave a Comment





Latest News Stories

MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
MH 114 June 2

Manhattan School Board Approves Staff Changes, Healthcare Extension in Special Session

Manhattan School District 114's Board of Education approved several personnel changes and a healthcare extension during a special meeting Monday evening, conducting most of its business in closed session. The...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting Briefs

School District 114 June 2 Meeting Briefs

Staff Departures: Manhattan School District 114 accepted the resignations of Emily Corcoran and Caroline Pesa-Miller, both effective at the end of the 2025 school year. The board approved both resignations...
Meeting Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...
MH VB 5--22

Manhattan Board Changes Meeting Time, Limits Public Comment

Village moves to 5:30 p.m. start time and reduces speaking period from five to three minutes The Village of Manhattan Board of Trustees approved two ordinance changes Tuesday that will...