Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission
County Board Abates Over $25 Million in Property Taxes for Bond Payments
School Board Approves ‘Board Book Premier’ for Paperless Meetings
Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment
District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service
Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025
Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall
Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases
Manhattan School District 114 Approves $41.5 Million Budget for FY26
Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign