Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Leave a Comment





Latest News Stories

will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
MH VB 6-3

Kelly Gibbons Named Chairperson of Manhattan Planning and Zoning Commission

The Manhattan Village Board appointed Kelly Gibbons as chairperson of the Planning and Zoning Commission for a two-year term running through May 1, 2027. Gibbons, who already serves as a...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....
Meeting Briefs

Manhattan Village Board Briefs

Banks Farm Development: The village board approved six separate resolutions demanding payment on letters of credit for various phases of the Banks Farm Development Villas of Prairie Trails project, covering...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications

A new Wendy's restaurant is set to be built at the northwest corner of U.S. Route 30 and Frankfort Square Road after the Frankfort Village Board unanimously approved the project...
Frankfort-Village-Board-Meeting-Graphic

Historic Downtown Frankfort Property Granted Deck and Patio Variances

The owners of a historic mixed-use building in downtown Frankfort have received approval for six zoning variances to construct a new paver patio and a second-floor rear deck. The Frankfort...
MH 114 June 2

Manhattan School Board Approves Staff Changes, Healthcare Extension in Special Session

Manhattan School District 114's Board of Education approved several personnel changes and a healthcare extension during a special meeting Monday evening, conducting most of its business in closed session. The...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment

The Frankfort Village Board authorized over $1.3 million in payments at its meeting Monday, with nearly half of the total amount covering the village's annual insurance premiums. Trustees unanimously approved...
Meeting Briefs

School District 114 June 2 Meeting Briefs

Staff Departures: Manhattan School District 114 accepted the resignations of Emily Corcoran and Caroline Pesa-Miller, both effective at the end of the 2025 school year. The board approved both resignations...
Meeting Briefs

Meeting Briefs: Frankfort Village Board for June 2, 2025

Wendy's Project Approved with Multiple Variances: The Village Board gave final approval for a new Wendy's restaurant at U.S. Route 30 and Frankfort Square Road. The project required a major change...
frankfort-park-district.1

Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute

The Frankfort Park District Board of Commissioners entered into a closed executive session on Tuesday, May 27, to discuss pending litigation concerning the Five Oaks Park parcel, signaling a deepening...