WCO-Landfill-8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary:

The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on schedule. Consultants presented detailed findings from the completed geological and hydrogeological fieldwork, which will inform the final engineering and design of the new landfill area to ensure public and environmental safety.

Landfill Expansion Key Points:

  • Drilling of nine new borings and continuous soil and bedrock sampling for the expansion area is complete, with samples being sent for extensive laboratory analysis.

  • Fourteen new piezometers, or monitoring wells, have been installed to characterize groundwater conditions and will be used for an impact evaluation model.

  • Engineers are refining the expansion’s design, including adjusting the northern boundary to maximize airspace and designing a V-notched base for efficient leachate collection.

  • Despite the fieldwork phase taking slightly longer than anticipated, project consultants confirmed the overall expansion timeline has not been delayed.

The Will County Landfill Committee on Thursday received a detailed update on the extensive site investigation for the planned expansion of the county landfill, learning that the project remains on schedule as engineers begin analyzing a trove of geological data.

A consultant for the project, Mr. Fallon, walked committee members through the now-completed fieldwork phase, which involved drilling nine borings as deep as 140 feet to characterize the soil, clay, and bedrock at the proposed expansion site. He explained that the purpose of the in-depth investigation is to provide engineers with the necessary data to design a site that protects public health, safety, and welfare.

“We have logged and continuously sampled nine additional borings to supplement that information at the existing facility,” Fallon stated. “Those samples have all been delivered to the lab. And actually… we have already received back I would say about 75% of those analytical results.”

The investigation included collecting undisturbed soil samples using Shelby tubes and rock cores to conduct a battery of laboratory tests. These tests, Fallon explained, measure properties like soil density, moisture content, permeability, and shear strength. The results are critical for engineering calculations that ensure the stability of the landfill’s slopes and foundation.

In addition to soil stability, the investigation is focused on groundwater. Fourteen new piezometers—small-diameter wells—have been installed at various depths to monitor different water-bearing zones. This data will be used to create a groundwater impact evaluation model.

“We’ll take the landfill design once it’s once our engineers have developed that and then we’ll… place it into the into the geologic system,” Fallon said in response to a question from member Dawn Bullock. “And then we’ll assume that it’s leaking and we’ll evaluate… after 100 years after closure what are the what are the concentrations of this hypothetical plume at the zone of attenuation.”

Fallon noted that this modeling is a state requirement for the sighting application.

The data is already informing design tweaks. Stormwater modeling has shown that the planned retention ponds are larger than necessary, allowing engineers to push the landfill’s northern boundary slightly to “eek out a little more airspace.” They are also designing the base grades with a “V-notch design” to better channel leachate to a sump location for extraction.

County Board Speaker Joe VanDuyne asked if the water from the underlying aquifer could be utilized by the county. Fallon explained that this would be out of the question, citing both the unsuitability of the small monitoring wells for water supply and a deed restriction on the property. “We have a deed restriction we’re not allowed to use any of the water for drinking purposes,” he said.

Vice-Chair Kelly Hickey, who chaired the meeting, asked if there were any changes to the project’s timeline.

“We haven’t had a delay in the project yet,” Fallon responded. “The field investigation did take a little longer than we than we had thought it would… but within the larger framework of the project, I feel like we’re still on schedule.”

Leave a Comment





Latest News Stories

Frankfort-Township-Logo-Graphic

Outdoor Bar Expansion Gets Green Light from Frankfort Township

The Frankfort Township Board has approved a special use permit that will allow a bar in an unincorporated area to expand its service outdoors. The unanimous decision was made during...
Frankfort-Township-Logo-Graphic

Meeting Briefs: Frankfort Township Board for April 14, 2025

The Frankfort Township Board of Trustees met on Monday, April 14, 2025, to address zoning matters and new business. The board took a firm stance against government consolidation, unanimously passing...
Manhattan Township

Manhattan Township Recommends Denial of Bruns Road Rodeo Permit Amid Neighbor Objections

The Manhattan Township Board unanimously recommended that Will County deny a permit for a large-scale commercial rodeo on Bruns Road, following a contentious public hearing where neighbors cited a history...
Manhattan Township

Road Contract Awarded as Township Races Against Bridge Funding Deadline

The Manhattan Township Highway Department has awarded a $91,000 contract for its annual road resurfacing program, while simultaneously facing a critical deadline that puts $500,000 in county funding for a...
Manhattan Township

Manhattan Township Halts Electric Aggregation Program, Citing Poor Pricing

Residents in unincorporated Manhattan Township will no longer be enrolled in a group electricity purchasing plan after the Township Board voted unanimously not to renew its electric aggregation contract. The...
Manhattan Township

Meeting Briefs: Manhattan Township for April 8, 2025

Assessor’s Office to Replace Server, Receives New Tax Multiplier: Assessor Joe Oldani reported that the township’s server is not compliant with current security methods and must be replaced by the end...
MFPD-Logo-Fire District

Fire District Receives Clean Audit, Adds 9 New Firefighters Despite Staff Departures

The Manhattan Fire Protection District received a clean audit report for fiscal year 2023 while addressing staffing challenges with nine new part-time firefighters set to join the department at the...
MFPD-Logo-Fire District

Construction Manager Decision Delayed for New Fire Station Project

The Manhattan Fire Protection District has postponed a decision on hiring a construction management company for its new fire station project while fee structures are finalized. Board members met with...
MFPD-Logo-Fire District

Manhattan Fire District March 17 Meeting Briefs

Vehicle Updates Progressing: The new Tahoe ordered last year has arrived but will require several months before entering service. The ambulance damaged in December's crash is currently at the body...
Manhattan Township

Manhattan Township to Fight State Consolidation Bills, Citing Threat to Local Services

The Manhattan Township Board is mounting a formal opposition to a series of state bills that officials believe threaten the existence of township governments across Illinois. During their monthly meeting...
Manhattan Township

Massive Battery Storage Facility Proposed in Manhattan Township, Could Be “Largest in Illinois”

A proposal for a 15-acre battery storage facility that could be the "largest substation in Illinois" is under consideration in Manhattan Township, a project that could reshape a portion of...
Manhattan Township

Proposed Bruns Road Rodeo Sparks Concerns Over Safety, Zoning, and Past Violations

A proposal to host a large, multi-weekend rodeo on Bruns Road has raised numerous red flags for the Manhattan Township Board, which cited concerns ranging from public safety and zoning...
Manhattan Township

Soltage Solar Farm Clears County Committee; Township Eyes Aesthetic Improvements

The proposed Soltage Solar Farm has passed a key hurdle, gaining approval from the Will County Land Use Committee in a 5-1 vote, Manhattan Township Supervisor James 'Jim' Walsh reported...
Meeting Briefs

Meeting Briefs: Manhattan Township for March 11, 2025

Dial-A-Ride Service to be Absorbed by County: The Southwest Dial-A-Ride service is being absorbed by the larger Will County Dial-A-Ride service, which is offered through PACE. Township officials expressed hope that...
Blue flasher light of siren of police car

Manhattan Police Reports

Disclaimer: Charges against each defendant are merely an accusation, with all defendants presumed innocent unless proven guilty in a court of law. On March 5, officers stopped Leal Acosta, Julio C (25)...