Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Mental Health Board Updates Committee on 2026 Grant Cycle and Funding Priorities
Manhattan Board Finalizes Round Barn Annexation, Sets New Year’s Eve Ball Drop
PZC Approves Homer Township Landscape Business Despite Neighbor Concerns; Adds Berm Condition
JJC Foundation Executive Director Retires Following $2.3 Million Estate Gift
Lincoln-Way Board Approves $92.5 Million Tax Levy for 2025
Chicago council, ‘starting to legislate,’ sends $16.7 billion budget to mayor
Manhattan Board Approves Kubota RTV Purchase for Sidewalk Plowing
Hegseth promises to fix barracks, but work could take time
‘Long overdue’: Praise for HHS’ action to bar taxpayer-funded sex-change procedures
Gas prices drop, but taxes make Illinois pricier than Midwest neighbors
Liquor License Amendments Approved for Frankfort, Joliet, and Lockport Businesses
Meeting Summary and Briefs: Will County Planning and Zoning Commission for December 16, 2025