Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete
Manhattan Township Meeting | June 2025
Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee Street Bridge project set to go out for bid in July. The Road District also reported that only 2.5 miles of gravel roads remain in the township.
Township Road Projects Key Points:
-
The Baker Road Bridge construction is 45% finished.
-
The Kankakee Street Bridge project will be put out for bid in July, with construction scheduled to begin in April 2026.
-
After removing Barton Road from the gravel system, the township now has only 2.5 miles of gravel roads left to maintain.
-
The Road District expects to receive a new truck in July.
Manhattan Township is making steady progress on its major infrastructure projects, Highway Commissioner Jim Baltas reported on Tuesday, June 10, 2025.
Baltas informed the township board that construction on the Baker Road Bridge is now 45% complete. This key project aims to replace an aging structure and improve transportation in the area.
Meanwhile, the township is preparing to move forward with another significant project. The Kankakee Street Bridge replacement will be put out for bid in July. Construction for this project is currently scheduled to begin in April 2026.
In his report, Baltas also noted a milestone in the road district’s long-term goal of reducing gravel roads. Barton Road has been converted from gravel, leaving only 2.5 miles of gravel roads remaining in the entire township. To aid in maintaining these roads, the district is also expecting the delivery of a new truck in July.
Latest News Stories
Executive Committee Advances $15,000 Strategic Plan Initiative
Rich States Poor States: Tax policy largely determines states’ economic competitiveness
P&Z Commission Overrides Staff Denials, Rescuing Special Use Permits for Joliet Wedding Venue and Romeoville Barge Terminal
Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover
P&Z Approves Lockport Bounce House Business Expansion
78 pro-life orgs ask DOJ to stop undermining state laws by favoring aborting drug industry
Lincoln-Way East Boys Outpace West and Stagg to Claim SWSC Triangular Victory
Lincoln-Way East Girls Track Dominates Triangular Meet Against West and Stagg
Illinois Quick Hits: Two of ComEd four released; new trial expected
Five Home Runs Power Lincoln-Way West Past Bradley-Bourbonnais 9-1
Meeting Summary and Briefs: Village of Manhattan Board of Trustees for April 7, 2026
Will County Treasurer Seeks Policy on Cash Payments as U.S. Mint Discontinues the Penny
Lend a hand this spring at Volunteer Morning programs