Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete
Manhattan Township Meeting | June 2025
Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee Street Bridge project set to go out for bid in July. The Road District also reported that only 2.5 miles of gravel roads remain in the township.
Township Road Projects Key Points:
-
The Baker Road Bridge construction is 45% finished.
-
The Kankakee Street Bridge project will be put out for bid in July, with construction scheduled to begin in April 2026.
-
After removing Barton Road from the gravel system, the township now has only 2.5 miles of gravel roads left to maintain.
-
The Road District expects to receive a new truck in July.
Manhattan Township is making steady progress on its major infrastructure projects, Highway Commissioner Jim Baltas reported on Tuesday, June 10, 2025.
Baltas informed the township board that construction on the Baker Road Bridge is now 45% complete. This key project aims to replace an aging structure and improve transportation in the area.
Meanwhile, the township is preparing to move forward with another significant project. The Kankakee Street Bridge replacement will be put out for bid in July. Construction for this project is currently scheduled to begin in April 2026.
In his report, Baltas also noted a milestone in the road district’s long-term goal of reducing gravel roads. Barton Road has been converted from gravel, leaving only 2.5 miles of gravel roads remaining in the entire township. To aid in maintaining these roads, the district is also expecting the delivery of a new truck in July.
Latest News Stories
Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township
Will County Survey Reveals Widespread AI Use as IT Drafts Governance Policy
Meeting Summary and Briefs: Will County Board for March 19, 2026
AARP Urges Will County to Ban Cryptocurrency Kiosks Amid Exploding Senior Fraud Rates
Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon
Sunny Hill Nursing Home Implements Enhanced Infection Control and Safety Measures
Consultant Updates Finance Committee on Homer Glen Police Cost Study
Lincoln-Way West Girls Display Middle-Distance Strength at Central Invitational
Lincoln-Way West Secures Eight Individual Victories, Takes Third in Varsity A at Best 4 Invitational
Oswego Outlasts Lincoln-Way West 5-3 in Nine-Inning Thriller
Manhattan Renews Will County LPR Camera Agreement as Police Chief Highlights Crime-Solving Successes
Manhattan 114 Board Advances Facility Upgrades and Reviews Transportation Bids
Fish fight: action-packed eagle pic wins March photo contest