Kankakee Street Bridge Project to Go to Bid in July; Baker Road Bridge 45% Complete
Manhattan Township Meeting | June 2025
Article Summary: Manhattan Township’s infrastructure program is moving forward on multiple fronts, with the Baker Road Bridge reconstruction now 45% complete and the larger Kankakee Street Bridge project set to go out for bid in July. The Road District also reported that only 2.5 miles of gravel roads remain in the township.
Township Road Projects Key Points:
-
The Baker Road Bridge construction is 45% finished.
-
The Kankakee Street Bridge project will be put out for bid in July, with construction scheduled to begin in April 2026.
-
After removing Barton Road from the gravel system, the township now has only 2.5 miles of gravel roads left to maintain.
-
The Road District expects to receive a new truck in July.
Manhattan Township is making steady progress on its major infrastructure projects, Highway Commissioner Jim Baltas reported on Tuesday, June 10, 2025.
Baltas informed the township board that construction on the Baker Road Bridge is now 45% complete. This key project aims to replace an aging structure and improve transportation in the area.
Meanwhile, the township is preparing to move forward with another significant project. The Kankakee Street Bridge replacement will be put out for bid in July. Construction for this project is currently scheduled to begin in April 2026.
In his report, Baltas also noted a milestone in the road district’s long-term goal of reducing gravel roads. Barton Road has been converted from gravel, leaving only 2.5 miles of gravel roads remaining in the entire township. To aid in maintaining these roads, the district is also expecting the delivery of a new truck in July.
Latest News Stories
Illinois House pushes through bill restricting ICE detention centers in state
Cheaper gas could take time amid tentative ceasefire
Trump says military remains in place as talks with Iran set to begin
Illinois Quick Hits: Ex-nonprofit exec sentenced for state, federal grant fraud
Will County Prepares for Route 66 Centennial with $3.4 Million in Grant Projects
Lawmaker calls for department reform supporting Illinois families with disabled children
Lawyers’ ‘misleading statements’ hang cloud over college finaid class action
Ceasefire impact holds across markets despite varying reports on the Strait of Hormuz
SEC chairman returns ”first principles’ to public markets, supports Texas exchange
Complaint filed against AMA Foundation for racially discriminatory scholarships
Democrats vow to hold Bondi in contempt for refusing Epstein deposition
Commonwealth LNG signs supply deals with five major buyers
Lawmakers hear debate over data centers including revenue, headaches
Manhattan Unveils $32.8 Million FY2027 Budget Driven by Major Water and Sewer Upgrades