Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Spread the love

Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 6
Chance Showers And Thunderstorms
85° 70°

Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 64%

Leave a Comment





Latest News Stories

Screenshot 2026-02-22 at 5.06.42 PM

Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board voted to renew its contract for federal lobbyist services on Wednesday. Administration and supporting...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
manhattan elwood library graphic.4

Meeting Summary and Briefs: Manhattan-Elwood Public Library District for January 26, 2026

Manhattan-Elwood Public Library District Meeting | January 26, 2026 The Manhattan-Elwood Public Library District Board of Trustees held a highly productive, 52-minute regular meeting on Monday afternoon to authorize capital...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Screenshot 2026-03-22 at 12.12.19 PM

Manhattan School District Approves Tax Abatement and Fund Transfers

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: The Manhattan School District 114 Board of Education unanimously approved two key financial resolutions to transfer operational funds and...
Screenshot 2026-02-22 at 4.29.56 PM

Contracts Approved for New West Principal and District Technology Director

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board appointed Dr. Jennifer Killeen as the new Principal of Lincoln-Way West High School and Kyle...
manhattan elwood library graphic.2

Manhattan-Elwood Library Officially Adopts “Library of Things” Policies and Patron Waivers

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: Patrons will soon have new non-traditional borrowing options after the library board formally adopted policies and liability waivers to govern...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Screenshot 2026-02-22 at 5.06.42 PM

Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board approved the appointments of a new Chief of Staff and a Dean of Workforce...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
manhattan elwood library graphic.5

Library Board Proposes Land-for-Services Swap with Village of Elwood for Mississippi Lot

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: The Manhattan-Elwood Public Library District Board voted to offer a piece of property to the Village of Elwood in exchange...
Jackson Township Graphic.1 NEW

Meeting Summary and Briefs: Jackson Township Board for January 14, 2026

Jackson Township Board Meeting | January 14, 2026 The Jackson Township Board of Trustees met for its regular monthly meeting on January 14, 2026, at the Jackson Township Hall. Supervisor...
Screenshot 2026-03-22 at 12.12.19 PM

Winter Benchmark Data Highlights Growth in Reading and Math Across Manhattan District 114

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: Manhattan School District 114 administrators presented winter benchmark data showing strong academic growth across all grade levels, with significant...
Screenshot 2026-02-22 at 4.29.56 PM

Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board of Education approved a $479,526.96 contract with CDW to replace the indoor wireless access points...