Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 6
Mostly Cloudy then Chance Showers And Thunderstorms
85° 70°

Mostly Cloudy then Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 62%

Leave a Comment





Latest News Stories

Jackson Township Graphic.1 NEW

Jackson Township Prepares for Property Viability Pole Relocation, Addresses Northpoint Traffic Control

Jackson Township Board Meeting | January 14, 2026 Article Summary: The Jackson Township Board of Trustees discussed upcoming infrastructure and traffic management efforts, including potential compensation for moving a utility...
Screenshot 2026-03-22 at 12.12.19 PM

Manhattan School District Explores Alternative Transportation Amid Lincoln-Way Bus Challenges

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: The Manhattan School District 114 Board of Education is officially preparing to explore alternative busing options by issuing a...

Manhattan Ranked 6th Safest City in Illinois; Police Chief Warns of Traffic Accidents

Village of Manhattan Board Meeting | February 17, 2026 Article Summary: Mayor Mike Adrieansen announced that Manhattan has been ranked the 6th safest city in Illinois by SafeWise. Despite the...
Manhattan Township

Manhattan Township Assessor Initiates $13,500 Software Upgrade Amid Office Transition

Manhattan Township Meeting | January 13, 2026 Article Summary: Newly installed Manhattan Township Assessor Kristen Blaser announced the procurement of a modernized property assessment software system to overhaul the office's valuation...

Manhattan and New Lenox Renew Boundary Agreement Through 2046

Village of Manhattan Board Meeting | February 17, 2026 Article Summary: Following a public hearing, the Manhattan Village Board approved a new intergovernmental jurisdictional boundary line agreement with the Village...
Screenshot 2026-02-18 at 2.53.56 PM

Manhattan Board Approves Route 52 Safety Study and Multi-Use Path Engineering

Village of Manhattan Board Meeting | February 17, 2026 Article Summary: The Village of Manhattan Board of Trustees approved two separate resolutions regarding U.S. Route 52, authorizing a safety action...
Screenshot 2026-02-04 at 2.03.49 PM

State of the College: Local Legislators Bolster Student Support Services

Joliet Junior College State of the College | February 4, 2026 Article Summary: Joliet Junior College recognized state legislators for their direct support of the Wolves Essential Pantry, which aids...
Meeting Briefs

Meeting Summary and Briefs: Public Health & Safety Committee for February 5, 2026

Public Health & Safety Committee Meeting | February 5, 2026 Meeting SummaryThe Will County Board Public Health & Safety Committee met on Tuesday, February 5, 2026, to review departmental reports...
Joliet Junior College Graphic.5

State of the College: Dual Credit Program Enrollment Hits 6,000 Students

Joliet Junior College State of the College | February 4, 2026 Article Summary: The "12x12x12" dual credit initiative has driven a surge in high school participation, with nearly half of...
Will County Finance Logo

Meeting Summary and Briefs: Finance Committee for February 3, 2026

Finance Committee Meeting | February 3, 2026 The Will County Finance Committee met on Tuesday, February 3, 2026, to address critical facility needs and review the county's financial standing. The...
Will County P&Z Logo Planning Zoning

Fairmont Neighborhood Plan Update Prioritizes Infrastructure and Beautification Following Demographic Shift

Planning and Zoning Commission Meeting | February 3, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously approved an update to the Fairmont Neighborhood Plan, addressing significant demographic...
Will County Board Graphic.04

Health & Safety Committee: Monee Church Kitchen Project Highlighted in County Health Impact Report

Public Health & Safety Committee Meeting | February 5, 2026 Article Summary: The Will County MAPP Collaborative presented its impact report, highlighting ARPA-funded community kitchen projects in Monee and Joliet...
Screenshot 2026-02-04 at 2.03.49 PM

State of the College: President Namuo Pushes for Bachelor’s Degrees, Cites Record Graduation Rates

Joliet Junior College State of the College | February 4, 2026 Article Summary: JJC President Dr. Clyne Namuo highlighted the college’s legislative push to offer bachelor's degrees in applied fields...
Will County Finance Logo

Emergency Freezer Replacement Approved for Adult Detention Facility

Finance Committee Meeting | February 3, 2026 Article Summary: The committee authorized an emergency expenditure of $155,000 to replace a failed walk-in freezer system at the Adult Detention Facility (ADF)....
Will County Board Graphic.01

Meeting Summary and Briefs: Legislative Committee for February 3, 2026

Legislative Committee Meeting | February 3, 2026 The Will County Legislative Committee convened on Tuesday, February 3, 2026, to finalize its federal priorities and receive updates on state and national...