Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 5
Chance Showers And Thunderstorms
87° 67°

Chance Showers And Thunderstorms

💨 5 mph 💧 32%

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Executive Committee Advances Dissolution of Southeast Joliet Sanitary District

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee moved forward with two resolutions to facilitate the dissolution of the Southeast Joliet Sanitary District...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Board Legislative Committee for January 6, 2026

Will County Board Legislative Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Legislative Committee met on Tuesday, January 6, 2026, to finalize the county’s state and...
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...
Will County Board Graphic.03

Executive Committee: Relaxes Rules for Retiring Employee Proclamations

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee voted to amend county board rules to allow proclamations honoring retiring county employees to pass...
Will County Board Graphic.02

Lobbyist Updates: State Session Resumes; Transit Safety Concerns Raised

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: State lobbyists briefed the Will County Legislative Committee on the upcoming General Assembly session, noting a likely focus...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for January 6, 2026

Will County Board Finance Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Finance Committee met on Tuesday, January 6, 2026, to handle a light agenda of routine...
Will County Board Graphic.04

Capital Imp Committee: Facilities Director Reports on VAC Progress and Critical Health Department Elevator Repairs

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:Facilities Director Bill Fern provided updates on major renovation projects, including the completion of the Court Annex and the...
Will County Board Graphic.01

‘Good Food For All’ Initiative Proposes Local Agricultural Asset Mapping for Will County

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: Bob Heuer of HNA Networks presented a "Good Food For All" initiative to the Public...
Will County Board Graphic.03

Public Works Committee Advances $3.2 Million Engineering Contract for Mills Road Reconstruction

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The committee forwarded a resolution to award a $3.2 million contract to HDR Engineering, Inc. for...
Will County Board Graphic.04

Board Members Debate “Commitment to Truth” in Media Resolution

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: A proposal to demand the reinstatement of the "Fairness Doctrine" for news media sparked a philosophical debate on...
Will County Board Graphic.01

Executive Committee: Speaker VanDuyne and Member Butler Clash Over Removal of Committee Chair

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: A heated exchange erupted during the January 8 Executive Committee meeting when Member Daniel Butler challenged Speaker Joe...
Will County Finance Logo

Finance Committee: County Appropriates Fees from $25 Million Wilmington Warehouse Project

Will County Board Finance Committee Meeting | January 6, 2026 Article Summary: The Finance Committee approved the appropriation of an administrative fee tied to a major industrial renovation in Wilmington....
will county board meeting.6

Capital Imp Committee: Begins Drafting Policy to Regulate Artificial Intelligence in County Government

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:The Will County Board Capital Improvements and IT Committee began formulating a comprehensive policy regarding the use of Artificial...