Will County Finance Committee Meeting October 7, 2025

Article Summary: Will County’s Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the fiscal year through August, after a summer plagued by mechanical failures, power outages, and maintenance issues that hampered production. Despite the challenges, officials remain optimistic about closing the financial gap by the end of the fiscal year, pointing to a strong performance in September and the plant’s long-term revenue potential.

RNG Plant Performance Key Points:

  • As of August 31, 2025, the RNG plant reported a net loss of $459,484.52 for the fiscal year.

  • Production in July and August fell below targets due to valve failures, sensor issues, severe storms, and computer errors.

  • Production exceeded targets in June, and a strong rebound in September has officials hopeful of breaking even for the year.

  • The plant is in its third year of repaying a 12-year, $48 million green bond used for its construction.

JOLIET, IL – Will County’s gas-to-energy plant has faced a series of operational challenges this summer, resulting in a net loss of $459,484 as of August 31, according to a report presented to the Finance Committee on Tuesday, October 7, 2025.

Greg Komperda, the RNG Facility Project Manager, detailed a difficult summer for the plant, which converts landfill gas into pipeline-quality natural gas. While production in June exceeded its target, generating over 73,000 Million British Thermal Units (MMBtu), performance dipped significantly in July and August.

In July, the plant produced 68,768 MMBtu against a target of 71,300 MMBtu. August production fell further to 64,446 MMBtu. Komperda attributed the shortfalls to a string of problems, including:

  • Valve failures in the nitrogen removal system, likely caused by moisture in the compressed air supply.

  • A delivery rejection from the pipeline operator due to faulty sensors at the delivery point.

  • Ongoing landfill wellfield maintenance, which temporarily reduced the flow of gas to the plant.

  • Sporadic power outages caused by severe storms in late August.

  • Computer errors in the nitrogen control system that required the manufacturer to reprogram it.

Despite the setbacks, Komperda reported that production rebounded in September to over 69,000 MMBtu. “We are closing in on the gap,” he said. “If we could maintain production at a good level, we have a chance of closing that gap in on our under revenue.”

Board members questioned the operational reliability and long-term financial viability of the project. In response to questions about frequent power outages, officials stated that installing a backup generator system capable of powering the plant was not financially feasible. Similarly, a significant solar array to offset the plant’s high electricity consumption—more than all other county facilities combined—would require 70-80 acres and cost an estimated $28 to $48 million.

Board member Daniel J. Butler highlighted the project’s long-term investment perspective. He confirmed with officials that the plant was financed with a 12-year, $48 million green bond. With three years of payments made, the facility has nine years of debt service remaining.

“After 12 years, we are going to be having generate extra money and it should lessen the tax burden,” Butler said, framing the current challenges within the context of the plant’s projected 35-plus-year lifespan. “Here we are making an investment into the future for the people of Will County.”

Manhattan Weather Full forecast →
Today Jun 5
Chance Showers And Thunderstorms
87° 67°

Chance Showers And Thunderstorms

💨 5 mph 💧 32%

Leave a Comment





Latest News Stories

will county board graphic

Public Health Committee Chair Demands Animal Control Agreements for Crete, Monee

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: During the January 7, 2026, Public Health and Safety Committee meeting, Chair Daniel Butler demanded...
Will County Board Graphic.03

Public Works Committee Considers Taking Over Kankakee County Line Road to Expedite Bridge Repairs

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The Will County Division of Transportation (WCDOT) is exploring a jurisdictional transfer of a section of...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for January 6, 2026

Village of Manhattan Board of Trustees Meeting | January 6, 2026 The Manhattan Village Board of Trustees met on Tuesday, January 6, 2026, to handle routine business and address immediate...
Wetzel

Peotone Man Charged With Disorderly Conduct, Criminal Damage at New Lenox Target

A 45-year-old Peotone man has been charged with disorderly conduct and criminal damage to property following an incident at a New Lenox Target store, according to police. New Lenox police...
Will County Board Graphic.04

Executive Committee: Update to Land Resource Management Plan; Solar Farms and Rural Zoning Dominate Discussion

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Will County Executive Committee initiated the first major update to the county’s Land Resource Management Plan since...
Will County Logo Graphic

Will County Committee Adds Path to Citizenship Support to Federal Agenda

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: The Will County Board Legislative Committee voted on Tuesday, January 6, 2026, to amend its federal legislative agenda...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township Board for November 11, 2025

Manhattan Township Board Meeting | November 11, 2025 The Manhattan Township Board met on Tuesday, November 11, 2025, at the Manhattan Township Hall. Supervisor Jim Walsh called the meeting to...
Will County Board Graphic.03

Health Department Outlines Major Reduction in Consensus Vaccine Schedule

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: Will County Health Department Executive Director Elizabeth Bilotta clarified changes to the childhood immunization schedule,...
Will County Board Graphic.04

Public Works Committee Forwards Condemnation Proceedings for Francis and Marley Road Improvements

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The committee authorized the Will County State’s Attorney’s Office to proceed with condemnation cases to acquire...
Will County Finance Logo

Finance Committee: Scholarship Tax Credit Discussion Halts

Will County Board Finance Committee Meeting | January 6, 2026 Article Summary: A heated procedural debate erupted at the Will County Board Finance Committee meeting when a member attempted to...
norovirus

Will County Health Department Reports Rise in Respiratory Illnesses, Updates on Facility Issues

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: At the January 7, 2026, meeting, Executive Director Elizabeth Bilotta reported a spike in respiratory...
Will County Board Graphic.01

Public Works Committee Delays Vote on State Police License Plate Cameras Amid Privacy Concerns

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The Will County Board Public Works & Transportation Committee voted to postpone a decision on an...
Village of Manhattan Logo Graphic

Village Staff Updates Board on Housing Development, Infrastructure Projects, and Police Activity

Village of Manhattan Board of Trustees Meeting | January 6, 2026 Article Summary: Village staff and officials provided updates on several key local projects during Tuesday's meeting, including a new...
Manhattan Township

Township Reviews Tax Levies; Bridge Construction Costs Rise

Manhattan Township Board Meeting | November 11, 2025 Article Summary: The Manhattan Township Board reviewed tentative tax levies for the upcoming year, with the Road District facing increased costs due...
Gilbert Bernal Sr

Flint Man Charged with 1988 Murder of Wife Joan Bernal Following Cold Case Breakthrough

Article Summary: Gilbert Bernal Sr., 82, appeared in Will County court facing first-degree murder charges connected to the 1988 disappearance of his wife, Joan Bernal, following a sealed indictment returned...