Will County Awards $10.4 Million Contract for Bell Road Widening in Homer Glen Area

Spread the love

Will County Public Works & Transportation Committee Meeting October 7, 2025

Article Summary: The Will County Public Works & Transportation Committee on Tuesday confirmed the award of a $10.4 million contract to P.T. Ferro Construction Co. for the major reconstruction and widening of a segment of Bell Road. The project, spanning from 151st Street to Martingale Lane, is expected to begin in November 2025 and will include new sidewalks, storm sewers, and modernized traffic signals.

Bell Road Project Key Points:

  • P.T. Ferro Construction Co. was the low bidder for the project with a bid of $10,400,058.22.

  • The project involves roadway widening and reconstruction on Bell Road (County Highway 16) from 151st Street to Martingale Lane.

  • Work is scheduled to begin in November 2025 and is estimated to be completed by November 20, 2026.

  • The roadway will remain open during construction with periodic lane closures controlled by flaggers.

JOLIET, IL – A significant road improvement project is set to begin in the Homer Glen area next year after the Will County Public Works & Transportation Committee on Tuesday, October 7, 2025, approved a $10.4 million construction contract.

The committee unanimously confirmed the award to Joliet-based P.T. Ferro Construction Co., which submitted the lowest bid for the reconstruction and widening of Bell Road (County Highway 16) between 151st Street and Martingale Lane. The contract is for $10,400,058.22.

The project is a major undertaking aimed at improving traffic flow and safety along the busy corridor. According to a project summary from the Will County Division of Transportation, the scope of work includes roadway widening and reconstruction with new pavement, installation of sidewalks and storm sewers, and modernization of traffic signals. The project will also involve building a soldier pile retaining wall, new street lighting, and pavement markings.

Construction is slated to begin in November 2025, with an estimated completion date of November 20, 2026. Officials have stated that Bell Road will remain open to traffic throughout the construction period, though drivers should expect periodic lane closures controlled by flaggers.

The contract was awarded following a bid letting on September 17, 2025.

The resolution confirming the contract award will now go to the full Will County Board for final approval at its October 16 meeting. Funding for the improvements will come from a combination of sources, including Motor Fuel Tax, RTA Tax, and County Highway Tax funds.

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...
Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
Meeting Briefs

Meeting Summary and Briefs: Jackson Township Board for August 13, 2025

The Jackson Township Board took the next step in reviewing a proposed anaerobic digester project at its meeting on Wednesday, August 13, 2025, referring the plan from Elwood81, LLC, to...
Jackson Township

Jackson Township to Investigate Decade-Old High-Speed Rail Plan Through Elwood

Article Summary: Jackson Township officials are seeking information on a high-speed rail plan dating back to 2012 that would route a passenger line through the Elwood area. Supervisor Matt Robbins...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Park Board for August 14, 2025

The Manhattan Park Board made significant progress on its flagship Round Barn Farm project during its meeting on August 14, 2025. Commissioners unanimously approved hiring a new architect, Arete Design...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
jackson township graphic.1

Jackson Township Approves Settlement with Joliet, Union Pacific Over ICC Case

Article Summary: The Jackson Township Board unanimously approved a settlement agreement involving the City of Joliet and Union Pacific Railroad, formally resolving a multi-year case before the Illinois Commerce Commission....
Meeting Briefs

Meeting Summary and Briefs: Lincoln-Way Community High School District 210 Board of Education for September 18, 2025

The Lincoln-Way Community High School District 210 Board of Education on Thursday, September 18, 2025, formally adopted a $172.7 million budget for the 2025-2026 school year. The budget includes a...
manhattan park district graphic.1

Manhattan Park Board Deadlocks on Paying for Sports Complex Plan, Motion Fails

Article Summary: A proposal for the Manhattan Park District to fund an architectural concept plan for a new sports complex failed to pass on Thursday, August 14, 2025, after a...
manhattan elwood library graphic.5

Manhattan-Elwood Library Board Adopts Annual Budget and Appropriation Ordinance

Article Summary: The Manhattan-Elwood Public Library District Board of Trustees has formally adopted its budget for the upcoming fiscal year following a public hearing. The approval of the combined Budget...
lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...