Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Will County Board Graphic.04

Will County Targets May Draft for Comprehensive Artificial Intelligence Policy

Capital Improvements & IT Committee Meeting | March 2026 Article Summary:Will County is moving closer to adopting a formal Artificial Intelligence policy, with IT staff planning to deliver a comprehensive...
Manhattan Park District Graphic

Manhattan Park Board Abates Bond Taxes, Authorizes Legal Intervention in Large Tax Appeals

Manhattan Park Board Meeting | February 12, 2026 Article Summary: The Manhattan Park District Board of Commissioners passed a resolution authorizing legal counsel to intervene in property tax appeals exceeding...
Will County P&Z Logo Planning Zoning.2

P&Z Commission Approves Side Yard Setback Variance for Joliet Detached Garage

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a variance to reduce a side yard setback on...
Will County Board Graphic.01

Executive Committee Advances Sweeping Overhaul of Will County Business Regulations

Will County Executive Committee Meeting | March 12, 2026 Article Summary: Will County is poised to modernize its business regulations following the Executive Committee's unanimous approval of a massive ordinance overhaul....
manhattan fire district graphic logo.2

Manhattan Fire District Fills Full-Time Vacancy, Welcomes Part-Time Members and Interns

Manhattan Fire Protection District Meeting | February 17, 2026 Article Summary: Following a recent disability hearing, the Manhattan Fire Protection District is moving to fill an operational vacancy with a...
Will County Finance Logo

Will County Closes Out $16.2 Million Federal Rental Assistance Program, Transitions to Local Funding

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County has officially closed out its massive federal Emergency Rental Assistance program after distributing millions to keep nearly 2,000...
Will County P&Z Logo Planning Zoning

Meeting Summary and Briefs: Will County Planning and Zoning Commission for March 3, 2026

Will County Planning and Zoning Commission Meeting | March 3, 2026 Overall Meeting SummaryThe Will County Planning and Zoning Commission convened on Tuesday, March 3, 2026, to review a series...
will county Committee-Capital Improvement.Graphic

Will County Leaders Debate New Construction to Escape $1.2 Million in Leases

Capital Improvements & IT Committee Meeting | March 2026 Article Summary: The Will County Capital Improvements and IT Committee is aggressively exploring options to consolidate county offices and exit leased...
manhattan fire district graphic logo.3

Meeting Summary and Briefs: Manhattan Fire Protection District for February 17, 2026

Manhattan Fire Protection District Meeting | February 17, 2026 The Manhattan Fire Protection District Board of Trustees held its regular meeting on Tuesday, February 17, 2026, at Fire Station #81....
Will County Finance Logo

Opioid Settlement Grants Funnel Nearly $600,000 to Local Police and Community Programs

Will County Finance Committee Meeting | March 3, 2026 Article Summary: Will County is distributing a significant portion of its opioid settlement funds to hyper-local agencies, including the Peotone and Manhattan...
Will County Finance Logo

Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026

Will County Finance Committee Meeting | March 3, 2026 The Will County Board Finance Committee met on Tuesday to review a slate of year-end financial reports and approve routine budget...
Comptroller, state lawmaker call for federal tax credit scholarships

Comptroller, state lawmaker call for federal tax credit scholarships

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – As Illinois edges toward a decision with significant implications for families and students, State Rep. Regan...
Jackson Township Graphic.1 NEW

Jackson Township Board Approves Assessor’s Budget, Advances Electrical Pole Negotiations

Jackson Township Board Meeting | February 11, 2026 Article Summary: The Jackson Township Board of Trustees unanimously approved the Assessor's budget and reviewed ongoing easement negotiations involving ComEd and local...
Lincoln Way West Warriors Softball

Lincoln-Way West Softball Rolls to 4-0 with 9-0 Shutout Over Plainfield North

The Lincoln-Way West varsity softball team continued its dominant start to the 2026 season on Saturday morning, traveling to Plainfield North and delivering a decisive 9-0 shutout victory in non-conference...
Lincoln Way West Warriors Baseball

Early Offense, Stellar Pitching Lift Lincoln-Way West Past Wheaton North, 2-1

The Lincoln-Way West varsity baseball team relied on timely hitting and exceptional pitching to scrape out a tight 2-1 non-conference road victory over Wheaton North on Saturday afternoon. The Warriors...