Consensus for power supply solution still elusive

Consensus for power supply solution still elusive

Spread the love

(The Center Square) – Rapid expansion of data centers in the mid-Atlantic region has leaves its power grid’s operator, PJM, standing at a crossroads: how can electricity supply keep up with exponential growth in demand without spiking bills for ratepayers?

After a Wednesday meeting with all of the organizations members – which include utility companies, state regulators, power plants, transmission providers, project developers, and commercial and industrial businesses – there’s still no path forward.

This, despite 12 proposals put forward for a vote. None earned majority support.

“The growth of data centers is colliding with the reality of the power grid,” said Tom Rutigliano, senior advocate for climate and energy at Natural Resources Defense Council. The advocacy group worked with Sen. Katy Fry Hester, D-Md., on one of the rejected plans.

Rutigliano told The Center Square that data centers are showing up and quickly adding cities’ worth of electric demand to the grid. Figuring out how to build power plants quickly enough to meet that demand is a $100 billion question, and reliability is at stake.

He surmises that PJM members ultimately backed proposals that served their own interests, preventing any real solution from advancing and leaving the grid’s board of directors with a hard choice – one he is optimistic will incorporate the best of each plan.

“We hope they fulfill their obligation to the 67 million people in the PJM region and commit to protecting reliability, treat all customers fairly, and not subsidize data centers at public expense,” Rutigliano said.

In addition to grappling with the core issues of reliability and affordability, open access is just as critical, Rutigliano said. It ensures all generators, including clean energy projects, have an equal opportunity to connect to the grid.

He warned that some proposed fast-track processes would heavily favor large fossil fuel plants, creating a permanent two-tier system where fossil fuel “gets a kind of concierge class connect to the grid and clean energy sits in coach.” From where NRDC sits, he added, that would be an unacceptable outcome.

Rutiglio acknowledged that while renewables alone aren’t enough to guarantee grid reliability, strategically combining them with storage and maintaining a diverse energy mix can create a reliable grid.

It is absolutely feasible, he said, to achieve 80-95% renewable integration. And, though the last stretch is the most difficult, it’s nowhere near being a problem – renewables make up single-digit percentages on PJM’s grid.

He said that renewables, combined with energy storage, can be built far faster than new gas turbines; often in 18 to 24 months, compared to years-long turbine waitlists and pipeline delays. Because storage is quicker to deploy and easier to site, he hopes the final policy outcome will encourage tech companies toward large-scale storage solutions. The goal, he added, isn’t to block data centers but to ensure they don’t shift risks onto the public, which is the goal of the “bring your own” proposals.

Roughly one-third of a data center’s cost is the power plant needed to serve it, he stated, and under the current system, taxpayers foot the bill for speculative projects – whether they get built or not – which he suggests is one of the main drivers for “bring your own.”

The voting at the Nov. 19 meeting resulted in none of the 12 proposal packages obtaining a requisite “passing” vote, Jeffrey Shields, PJM spokesman, told The Center Square via email.

“PJM opened this conversation about the integration of large loads and greatly appreciates our stakeholders for their contributions to this effort,” he said. ”The stakeholder process produced many thoughtful proposals, some of which were introduced late in the process and require additional development.”

This vote, Shields said, is advisory to PJM’s independent board, which can and does expect to act on large load additions to the system and will make its decision known in the next few weeks.

Leave a Comment





Latest News Stories

Lincoln Way West Warriors Softball

Lincoln-Way West Pitching Throws Perfect Three Innings in 15-0 Rout of Joliet West

The Lincoln-Way West varsity softball team delivered a flawless performance on Friday afternoon, combining a perfect game in the circle with a relentless offensive attack to defeat host Joliet West...
Manhattan Township

Manhattan Township Residents, Officials Mobilize Against Proposed EarthRise Solar Farm

Manhattan Township Meeting | February 10, 2026 Article Summary: Manhattan Township residents and the Green Garden Watershed Committee are organizing opposition to a massive proposed EarthRise solar farm, prompting the...
Lincoln Way West Warriors Softball

Six-Run Third Inning Propels Lincoln-Way West Softball Past Downers Grove South, 12-7

Downers Grove South jumped out to a quick four-run lead in the top of the first inning, but the Lincoln-Way West varsity softball team answered with a relentless offensive attack...
Lincoln Way West Warriors Baseball

Pettit Homers, Four Pitchers Combine for Shutout as Lincoln-Way West Blanks Riverside-Brookfield, 9-0

The Lincoln-Way West varsity baseball team put together a complete performance on Thursday, pairing an explosive offense with a stifling combined shutout to roll past visiting Riverside-Brookfield, 9-0, in non-conference...
Committee-Ad-Hoc.Graphic

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for March 10, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 The Will County Board Ad-Hoc Ordinance Review Committee met on Tuesday, March 10, 2026, to review a backlog...
Will County Board Graphic.02

Ad-Hoc Committee: Will County Sheriff’s Office to Acquire Decibel Meters for Noise Complaints

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: The Will County Sheriff's Office plans to purchase a fleet of certified decibel meters to accurately...
Will County Public Works Committee

Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday approved a request to allow commercial ingress...
Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...