Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road
Will County Executive Committee Meeting | February 11, 2026
Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in Wilmington. The railroad will contribute over $15 million toward the project and provide a one-time maintenance payment to the county.
Lorenzo Road Bridge Key Points:
-
Project: Construction of a grade separation bridge carrying Lorenzo Road (CH 80) over the BNSF Railroad tracks.
-
Location: 1.25 miles west of I-55 in County Board District 1.
-
Total Cost: The estimated total project cost is $28,717,523.80.
-
Railroad Contribution: BNSF will reimburse the county 100% of costs after the execution of ICC funds, up to a cap of $15,102,943.80.
-
Maintenance Fee: BNSF will pay Will County a one-time maintenance fee of $675,003.28 for the useful life of the overpass.
The Will County Board Executive Committee on Wednesday, February 11, 2026, approved Resolution 26-046, authorizing an agreement between the County and BNSF Railway for a major infrastructure project on Lorenzo Road.
The project involves constructing a bridge to separate the grade of Lorenzo Road (County Highway 80) from the BNSF rail line, located approximately 1.25 miles west of Interstate 55. The project aims to eliminate the at-grade crossing, improving safety and traffic flow in the heavy industrial corridor.
According to the agreement attached to the agenda, the total estimated cost of construction is $28,717,523.80. Under the terms of the deal, BNSF Railway will contribute significantly to the project. Once $12 million in Illinois Commerce Commission (ICC) funds are executed, BNSF will reimburse the county for remaining costs up to a cap of $15,102,943.80.
Additionally, the agreement stipulates that BNSF will provide a one-time lump sum payment of $675,003.28 to the county to cover future maintenance costs for the structure over its useful life. The county will be responsible for maintaining the roadway, bridge structure, and drainage.
The agreement requires the contractor to maintain strict safety clearances during construction, including 25 feet horizontally from the track centerline.
The measure was moved by Member Jacqueline Traynere and seconded by Member Denise Winfrey. It passed unanimously.
Latest News Stories
Behavioral Health Division Drops Wait Times, Reports Zero Opioid Deaths in February
Meeting Summary and Briefs: Village of Manhattan for March 3, 2026
Harris Drive Residents Plead for County Intervention Amid Failing Septic Systems and Flooding
Manhattan Village Board Approves Public Works Hires and Wastewater Equipment Purchase
Will County Sheriff’s Office Investigates Fatal Hit-and-Run in Homer Glen
Federal Funding Freezes Threaten Will County Public Health Programs Amid Ongoing Lawsuits
Manhattan Village Board Hears Pushback Against Massive Solar Farm and Industrial Expansion
Board Splits Along Party Lines to Approve 2026 Federal Legislative Agenda
Meeting Summary and Briefs: Will County Landfill Committee for February 10, 2026
Meeting Summary and Briefs: Will County Board for February 19, 2026
Board Approves Joliet Township Clean Fill Facility Despite Environmental Objections
Will County Board Unanimously Rejects Controversial Solar Farm in Troy Township