Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.20.34 AM

Will County Considers First Update to Wastewater Ordinance Since 2016

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is preparing to update its ordinance governing private wastewater systems, with proposed changes including the...
Screenshot 2025-10-10 at 12.12.11 PM

IDOT Plans to Invest Over $1.3 Billion in Will County Roads Through 2031

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Illinois Department of Transportation (IDOT) has allocated over $1.3 billion for road and bridge projects in...
Screenshot 2025-10-10 at 11.39.54 AM

Committee Advances 50% Increase in Mental Health Levy on 4-3 Vote

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a proposed $12 million levy for the Community Mental Health Board,...
Screenshot 2025-10-10 at 11.19.48 AM

Will County Poised to Launch Major Mental Health Initiative Based on Joliet Program’s Success

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Board Public Health & Safety Committee on Thursday considered establishing "Will County CARES," a...
Screenshot 2025-10-10 at 12.05.35 PM

Looming State Energy Bill Threatens to Further Limit County Control Over Solar and Wind Projects

Will County Legislative Committee Meeting October 7, 2025 Article Summary: A state energy bill likely to be considered during the fall veto session or next spring could further strip Will...
Screenshot 2025-10-10 at 11.52.31 AM

Controversial Immigrant Rights Resolution Postponed by Will County Board After Heated Debate

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Executive Committee voted to indefinitely postpone a contentious resolution titled "Declaring Will County's Commitment to Ensure Communities...
Screenshot 2025-10-10 at 11.39.50 AM

Will County’s Gas-to-Energy Plant Reports Nearly $460,000 Net Loss Amid Operational Setbacks

Will County Finance Committee Meeting October 7, 2025 Article Summary: Will County's Renewable Natural Gas (RNG) plant at the county landfill posted a net loss of nearly $460,000 for the...
Screenshot 2025-10-10 at 11.36.47 AM

Will County to Draft First-Ever Policy on Artificial Intelligence Use

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: The Will County Board's Capital Improvements & IT Committee has initiated the process of drafting a comprehensive...
Screenshot 2025-10-10 at 11.20.18 AM

Will County Sees 50% Drop in Opioid Deaths, But Alarming Rise in Suicides

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: Will County is experiencing a dramatic 50% reduction in opioid overdose deaths compared to last year, a...
Screenshot 2025-10-10 at 11.52.52 AM

Will County Board Backs Effort to Rename ‘Stigmatizing’ Chicago Sanitary and Ship Canal

Will County Executive Committee Meeting October 9, 2025 Article Summary: The Will County Board has thrown its support behind a regional effort to rename the Chicago Sanitary and Ship Canal,...
Screenshot 2025-10-10 at 12.12.04 PM

Access Will County Dial-a-Ride on Track for Full County-Wide Service in 2026

Will County Public Works & Transportation Committee Meeting October 7, 2025 Article Summary: The Access Will County dial-a-ride program is set for a major expansion in 2026, with plans to...
WCO 2025-09-27 at 9.04.36 AM

Divided Will County Board Authorizes Condemnation for 143rd Street Widening

Article Summary: Following intense debate and emotional public testimony, the Will County Board narrowly approved a resolution to begin condemnation proceedings for the controversial widening of 143rd Street in Homer...
Screenshot 2025-10-10 at 11.39.44 AM

Will County Committee Approves Preliminary $161.6M Tax Levy on Split Vote Amid Heated Debate Over Spending

Will County Finance Committee Meeting October 7, 2025 Article Summary: The Will County Finance Committee on Tuesday narrowly approved a preliminary $161.6 million property tax levy for 2025, which projects...
Screenshot 2025-10-10 at 11.36.42 AM

Will County Eyes Major Overhaul to Consolidate Scattered Government Offices

Will County Capital Improvements & IT Committee Meeting October 7, 2025 Article Summary: Will County officials are formally debating a new facilities master plan to address aging buildings and dozens...
Screenshot 2025-10-10 at 11.20.27 AM

Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act

Will County Public Health & Safety Committee Meeting October 2, 2025 Article Summary: The Will County Sheriff's Office reported a nearly 10% overall drop in crime compared to the same...