Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Leave a Comment





Latest News Stories

diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
District 114 Bus

Parents Voice Alarms Over Bus Safety, Lateness in Manhattan School District

Article Summary: Parents raised serious transportation safety and reliability concerns at the Manhattan School District 114 board meeting, including a harrowing account of a kindergartener being dropped off at the...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for September 16, 2025

The Manhattan Village Board took steps to prepare for future growth at its Tuesday meeting, awarding a contract of over half a million dollars to extend water and sewer infrastructure...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
Screenshot 2025-09-27 at 8.39.48 AM

Manhattan Police Department Promotes Garrison to Commander, Diaz to Sergeant

Article Summary: The Manhattan Police Department solidified its command structure with the promotions of William Garrison to the rank of Commander and Bryan Diaz to Sergeant, who were both officially...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for August 18, 2025

Manhattan Fire Protection District | August 18, 2025 Meeting The Manhattan Fire Protection District Board of Trustees focused on the future of its facilities and public safety at its meeting...
Screenshot 2025-09-27 at 8.36.16 AM

Village of Manhattan Honors St. Joseph’s Catholic School on its 100th Anniversary

Article Summary: The Village of Manhattan celebrated a major community milestone at its Tuesday board meeting, officially honoring St. Joseph's Catholic School for its 100th anniversary with a formal proclamation...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Screenshot 2025-09-27 at 8.36.16 AM

Manhattan Awards $547K Contract for US 52 Infrastructure Extension to Spur Growth

Article Summary: The Village of Manhattan has awarded a $547,449 contract to Speece Construction for a significant sewer and water main extension project along the US 52, Smith Road, and...
manhattan fire district graphic logo.3

Fire District to Address Safety at High-Accident Intersections with County DOT

Manhattan Fire Protection District | August 18, 2025 Meeting Article Summary: The Manhattan Fire Protection District will meet with the Will County Department of Transportation to provide data and seek...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for August 2025

Manhattan Township Meeting | August 2025 The Manhattan Township Board took steps to address the growing interest in renewable energy at its meeting on Tuesday, August 12, 2025, by scheduling...
Screenshot 2025-09-27 at 8.16.09 AM

Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate...