Manhattan District 114 Approves Asphalt and Door Contracts Amid Sweeping Summer Facilities Upgrades

Spread the love

Manhattan School District 114 Meeting | March 25, 2026

Article Summary: The Manhattan School District 114 Board of Education reviewed extensive capital improvement plans and approved specialized contracts for paving and door replacements across multiple campuses to address audits and aging infrastructure.

Manhattan District 114 Capital Projects Key Points:

  • The board unanimously approved an asphalt and curb installation contract with PT Ferro at Manhattan Junior High School, with completion targeted before graduation.

  • A separate independent contractor agreement was approved for door replacements at Anna McDonald and Manhattan Intermediate School to address 10-year audit findings.

  • Facilities staff are preparing for an estimated $105,000 HVAC repair project at Wilson Creek this summer, which will be funded through bond proceeds.

  • The district is advancing phase two of an LED lighting transition, utilizing ComEd incentives to replace outdated pendant and classroom lighting.

The Manhattan School District 114 Board of Education on Wednesday, March 25, 2026, laid the groundwork for a busy season of summer capital projects, unanimously approving two immediate infrastructure contracts while reviewing a slate of upcoming facility maintenance initiatives.

The special meeting heavily featured updates from Ryan McWilliams of the district’s building and grounds department, who provided a comprehensive rundown of the summer maintenance schedule and ongoing vendor negotiations.

The board took direct action on two immediate projects. First, the board unanimously approved an independent contractor agreement for door replacements at Anna McDonald and Manhattan Intermediate School (MIS). The work, scheduled for July, is a direct response to issues flagged during the district’s recent 10-year life safety audit. Board Member Brian Anderson noted that the project will replace numerous exterior hinges at the intermediate school that are currently failing and leaking hydraulic fluid.

The board also approved a contract with PT Ferro for asphalt and curb installation at Manhattan Junior High School. The paving project will focus on the concession area, and McWilliams indicated that a secondary phase involving a retaining wall will be brought to the board for approval in April. District officials noted they are pushing to have the area finished in time for the regional track meet and graduation ceremonies.

Beyond the approved contracts, McWilliams briefed the board on larger, looming infrastructure needs, specifically regarding HVAC and roofing systems.

The district recently conducted walkthroughs with 2010 Engineering to evaluate the heating and cooling systems at Anna McDonald and MIS. The engineering firm is currently drafting a full scope of work, which is expected to be substantial. McWilliams warned the board that if the firm recommends full boiler replacements, the project cost will increase significantly, likely reaching into the seven figures.

In the interim, the district plans to tackle a smaller HVAC stabilization project at Wilson Creek this summer. McWilliams described the work as a “non-intrusive” replacement of aging valves and actuators to rectify climate control issues. The project is estimated to cost around $105,000 and will likely be funded through available bond proceeds since it was not explicitly budgeted for the current fiscal cycle. At the same time, preventative maintenance is actively underway at Wilson Creek, with Johnson Controls wrapping up a three-day service to remove scaling and rust buildup from the building’s chillers.

“We got to make sure that we’re keeping the equipment that we have working effectively and efficiently,” McWilliams told the board.

The district is also pushing forward with phase two of its LED lighting transition. Having completed the initial phase, the district will now focus on replacing pendant lighting in the MIS library and old band room, as well as executing a complete lighting overhaul at Anna McDonald.

At Wilson Creek, the district plans to replace 4-foot fixtures with modern 2×2 drop-in LED panels across all classrooms. The upgraded system will feature motion sensors that automatically dim or shut off lights when a room has been empty for 15 minutes, generating long-term electricity savings calculated by ComEd’s energy incentive algorithms.

Additionally, the board discussed ongoing discussions with STR and Anthony Roofing regarding potential roof replacements or specialized coatings at the district’s buildings, though the project remains in a holding pattern as administrators weigh the considerable price differences between the two methods.

Finally, to manage the district’s outdoor athletic facilities, McWilliams reported the acquisition of a specialized John Deere ride-on field grooming machine. Sourced from Georgia after learning about the model from the New Lenox Rebels baseball organization, the machine is equipped with spike drags, a finishing drag, and a front plow to maintain the district’s baseball and softball fields.

Leave a Comment





Latest News Stories

Congratulations to Corporal Kurtis Ingram

Corporal Ingram completes elite leadership training program

Corporal Kurtis Ingram has successfully completed the School of Police Staff and Command (SPSC) at Northwestern University’s Center for Public Safety. The SPSC is an intensive 10-week program focused on...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for January 8, 2026

Will County Board Executive Committee Meeting | January 8, 2026 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, January 8, 2026, tackling a heavy agenda that included...
Fire-Ambulance-Rescue-Logo

Automatic Sprinklers Contain Industrial Fire in New Lenox

Article Summary: New Lenox firefighters responded to a machinery fire at a facility on Berens Drive early Tuesday afternoon, where the building's fire suppression system prevented the blaze from spreading....
The fire at Woldhuis Sunrise Greenhouse had the mutual aid of 19 other agencies-photo courtesy Woldhuis.

Blaze Destroys Building and Food Truck at Woldhuis Sunrise Nursery

By Andrea Arens A massive fire tore through Woldhuis Sunrise Nursery late Thursday morning, destroying one greenhouse building, a food truck, damaging another building and drawing firefighters from across the...
Screenshot

Manhattan PD Celebrates Officer Podkul’s 20th Anniversary

A familiar face in the Village is celebrating a major career milestone. The Manhattan Police Department recently recognized Officer Podkul for 20 years of dedicated service. Known for his work...
manhattan fire district graphic logo.3

Manhattan Woman Killed, Students Uninjured in Head-On School Bus Crash

Article Summary: A 24-year-old Manhattan woman died Thursday morning after her vehicle crossed the center line and collided head-on with a Manhattan School District 114 bus. While the driver of...
Pritzker signs Clean Slate Act to automatically seal some criminal convictions

Pritzker signs Clean Slate Act to automatically seal some criminal convictions

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker has signed legislation to automate the state’s record-sealing process for individuals with certain criminal...
Will County Board Graphic.02

Freight Clusters Drive Push for Overhaul of Wilmington-Peotone Road; County Advances Broader 2050 Plan

Will County Board Meeting | January 15, 2026 Article Summary: Citing the emergence of "new freight clusters," Will County is seeking federal support for a massive study to redesign 22...
sunny hill nursing home joliet il

Sunny Hill Administrator Defends Private Room Model Amidst Capacity Discussions

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: During the January 7, 2026, meeting, Sunny Hill Nursing Home Administrator Maggie McDowell reported a...
Manhattan School 114 Graphic.1

Manhattan School Board Votes to Adopt ‘Committee of the Whole’ Meeting Structure

Manhattan School District 114 Meeting | Jan. 14, 2026 Article Summary: The Manhattan School District 114 Board of Education decided to restructure its committee meetings, moving from separate committee sessions...
Elite private colleges can’t cap off price-fixing collusion class action

Elite private colleges can’t cap off price-fixing collusion class action

By Scott Holland | Legal NewslineThe Center Square A federal judge in Chicago has refused to end an antitrust class action complaint accusing elite universities of colluding in the financial...
Illinois Quick Hits: GOP gubernatorial forum set for Monday

Illinois Quick Hits: GOP gubernatorial forum set for Monday

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – All four Republican gubernatorial candidates are scheduled to participate in a forum in East Dundee on Monday....
lincoln way school district 210 logo.2

Lincoln-Way Board Approves Girls Flag Football for 2026-2027 Season

Lincoln-Way 210 Board of Education Meeting | Jan. 15, 2026 Article Summary: The Lincoln-Way Community High School District 210 Board of Education unanimously approved the addition of girls flag football...
WATCH: Ives investigates tax dollars for NGOs; Republicans say Pritzker raising energy prices

WATCH: Ives investigates tax dollars for NGOs; Republicans say Pritzker raising energy prices

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square's Greg Bishop talks live with Jeanne...
ICE hiring ban bill reignites SAFE-T Act fight at Illinois Capitol

ICE hiring ban bill reignites SAFE-T Act fight at Illinois Capitol

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A newly introduced bill that would bar former Immigration and Customs Enforcement agents from working in...