Manhattan District 114 Approves Asphalt and Door Contracts Amid Sweeping Summer Facilities Upgrades

Spread the love

Manhattan School District 114 Meeting | March 25, 2026

Article Summary: The Manhattan School District 114 Board of Education reviewed extensive capital improvement plans and approved specialized contracts for paving and door replacements across multiple campuses to address audits and aging infrastructure.

Manhattan District 114 Capital Projects Key Points:

  • The board unanimously approved an asphalt and curb installation contract with PT Ferro at Manhattan Junior High School, with completion targeted before graduation.

  • A separate independent contractor agreement was approved for door replacements at Anna McDonald and Manhattan Intermediate School to address 10-year audit findings.

  • Facilities staff are preparing for an estimated $105,000 HVAC repair project at Wilson Creek this summer, which will be funded through bond proceeds.

  • The district is advancing phase two of an LED lighting transition, utilizing ComEd incentives to replace outdated pendant and classroom lighting.

The Manhattan School District 114 Board of Education on Wednesday, March 25, 2026, laid the groundwork for a busy season of summer capital projects, unanimously approving two immediate infrastructure contracts while reviewing a slate of upcoming facility maintenance initiatives.

The special meeting heavily featured updates from Ryan McWilliams of the district’s building and grounds department, who provided a comprehensive rundown of the summer maintenance schedule and ongoing vendor negotiations.

The board took direct action on two immediate projects. First, the board unanimously approved an independent contractor agreement for door replacements at Anna McDonald and Manhattan Intermediate School (MIS). The work, scheduled for July, is a direct response to issues flagged during the district’s recent 10-year life safety audit. Board Member Brian Anderson noted that the project will replace numerous exterior hinges at the intermediate school that are currently failing and leaking hydraulic fluid.

The board also approved a contract with PT Ferro for asphalt and curb installation at Manhattan Junior High School. The paving project will focus on the concession area, and McWilliams indicated that a secondary phase involving a retaining wall will be brought to the board for approval in April. District officials noted they are pushing to have the area finished in time for the regional track meet and graduation ceremonies.

Beyond the approved contracts, McWilliams briefed the board on larger, looming infrastructure needs, specifically regarding HVAC and roofing systems.

The district recently conducted walkthroughs with 2010 Engineering to evaluate the heating and cooling systems at Anna McDonald and MIS. The engineering firm is currently drafting a full scope of work, which is expected to be substantial. McWilliams warned the board that if the firm recommends full boiler replacements, the project cost will increase significantly, likely reaching into the seven figures.

In the interim, the district plans to tackle a smaller HVAC stabilization project at Wilson Creek this summer. McWilliams described the work as a “non-intrusive” replacement of aging valves and actuators to rectify climate control issues. The project is estimated to cost around $105,000 and will likely be funded through available bond proceeds since it was not explicitly budgeted for the current fiscal cycle. At the same time, preventative maintenance is actively underway at Wilson Creek, with Johnson Controls wrapping up a three-day service to remove scaling and rust buildup from the building’s chillers.

“We got to make sure that we’re keeping the equipment that we have working effectively and efficiently,” McWilliams told the board.

The district is also pushing forward with phase two of its LED lighting transition. Having completed the initial phase, the district will now focus on replacing pendant lighting in the MIS library and old band room, as well as executing a complete lighting overhaul at Anna McDonald.

At Wilson Creek, the district plans to replace 4-foot fixtures with modern 2×2 drop-in LED panels across all classrooms. The upgraded system will feature motion sensors that automatically dim or shut off lights when a room has been empty for 15 minutes, generating long-term electricity savings calculated by ComEd’s energy incentive algorithms.

Additionally, the board discussed ongoing discussions with STR and Anthony Roofing regarding potential roof replacements or specialized coatings at the district’s buildings, though the project remains in a holding pattern as administrators weigh the considerable price differences between the two methods.

Finally, to manage the district’s outdoor athletic facilities, McWilliams reported the acquisition of a specialized John Deere ride-on field grooming machine. Sourced from Georgia after learning about the model from the New Lenox Rebels baseball organization, the machine is equipped with spike drags, a finishing drag, and a front plow to maintain the district’s baseball and softball fields.

Leave a Comment





Latest News Stories

Will County Board Graphic.02

Executive Committee Advances Dissolution of Southeast Joliet Sanitary District

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee moved forward with two resolutions to facilitate the dissolution of the Southeast Joliet Sanitary District...
Will County Board Graphic.01

Meeting Summary and Briefs: Will County Board Legislative Committee for January 6, 2026

Will County Board Legislative Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Legislative Committee met on Tuesday, January 6, 2026, to finalize the county’s state and...
Will County Logo Graphic

Meeting Summary and Briefs: Capital Improvements & IT Committee for January 6, 2026

Capital Improvements & IT Committee Meeting | January 6, 2026 Overall Meeting SummaryThe Will County Board Capital Improvements and IT Committee met on Tuesday, January 6, 2026, to discuss facility...
Will County Board Graphic.04

Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for January 7, 2026

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Overall Meeting SummaryThe Will County Board Public Health and Safety Committee met on Wednesday, January 7, 2026,...
Will County Board Graphic.03

Executive Committee: Relaxes Rules for Retiring Employee Proclamations

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: The Executive Committee voted to amend county board rules to allow proclamations honoring retiring county employees to pass...
Will County Board Graphic.02

Lobbyist Updates: State Session Resumes; Transit Safety Concerns Raised

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: State lobbyists briefed the Will County Legislative Committee on the upcoming General Assembly session, noting a likely focus...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for January 6, 2026

Will County Board Finance Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Finance Committee met on Tuesday, January 6, 2026, to handle a light agenda of routine...
Will County Board Graphic.04

Capital Imp Committee: Facilities Director Reports on VAC Progress and Critical Health Department Elevator Repairs

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:Facilities Director Bill Fern provided updates on major renovation projects, including the completion of the Court Annex and the...
Will County Board Graphic.01

‘Good Food For All’ Initiative Proposes Local Agricultural Asset Mapping for Will County

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: Bob Heuer of HNA Networks presented a "Good Food For All" initiative to the Public...
Will County Board Graphic.03

Public Works Committee Advances $3.2 Million Engineering Contract for Mills Road Reconstruction

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The committee forwarded a resolution to award a $3.2 million contract to HDR Engineering, Inc. for...
Will County Board Graphic.04

Board Members Debate “Commitment to Truth” in Media Resolution

Will County Board Legislative Committee Meeting | January 6, 2026 Article Summary: A proposal to demand the reinstatement of the "Fairness Doctrine" for news media sparked a philosophical debate on...
Will County Board Graphic.01

Executive Committee: Speaker VanDuyne and Member Butler Clash Over Removal of Committee Chair

Will County Board Executive Committee Meeting | January 8, 2026 Article Summary: A heated exchange erupted during the January 8 Executive Committee meeting when Member Daniel Butler challenged Speaker Joe...
Will County Finance Logo

Finance Committee: County Appropriates Fees from $25 Million Wilmington Warehouse Project

Will County Board Finance Committee Meeting | January 6, 2026 Article Summary: The Finance Committee approved the appropriation of an administrative fee tied to a major industrial renovation in Wilmington....
will county board meeting.6

Capital Imp Committee: Begins Drafting Policy to Regulate Artificial Intelligence in County Government

Capital Improvements & IT Committee Meeting | January 6, 2026 Article Summary:The Will County Board Capital Improvements and IT Committee began formulating a comprehensive policy regarding the use of Artificial...