Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county approved a cost-sharing agreement with a private developer to build shared stormwater management facilities that will serve both a new residential subdivision and the upcoming Laraway Road widening project.

Laraway Road / LNS Development Key Points:

  • Will County and LNS Development Group, LLC will co-fund shared stormwater infrastructure.

  • The county will pay an estimated $332,209.92 for its share of the detention facility and storm sewer upgrades.

  • The county is also paying LNS Development $19,862.03 to acquire 0.43 acres of right-of-way required for the Laraway Road widening project.

  • The Laraway Road project will widen the highway to four lanes between Cedar Road and Spencer Road.

Will County is leveraging private development to streamline its own infrastructure costs, approving an agreement with LNS Development Group, LLC on Tuesday, April 7, 2026, to construct shared stormwater facilities along Laraway Road in New Lenox.

The agreement centers on a parcel of land (PIN 15-08-35-100-011) where LNS Development is planning a new residential subdivision. Concurrently, Will County is engineering a major capacity project to widen Laraway Road (County Highway 74) from a two-lane road to a four-lane highway with a center barrier median from Cedar Road to Spencer Road.

Because both the county’s highway expansion and the private residential development require significant stormwater management, the two entities agreed to co-locate and share the costs of a detention facility and upgraded storm sewers on the developer’s parcel.

According to the engineer’s estimates provided in the agenda packet, Will County’s financial obligation for the construction of the shared improvements is capped at an estimated $332,209.92. This breaks down to $179,218.92 (21% of the total cost) for the detention basin, and $152,991.00 (100% of the required upgrades) to properly size the storm sewers to accommodate WCDOT drainage. LNS Development will cover the remaining construction costs.

Furthermore, the agreement secures the land Will County needs to physically widen the road. LNS Development will convey 0.43668 acres of right-of-way to the county in exchange for $19,862.03. In return, the county guarantees the developer’s vested rights to specific access points and drainage capacity along the newly widened highway.

The measure was passed unanimously and advances to the full County Board.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District Board of Trustees for June 16, 2025

The Manhattan Fire Protection District Board of Trustees learned that plans for a new fire station are on hold after construction bids came in over budget. Fire Chief Steve Malone...
manhattan fire district graphic logo.2

Fire District Eyes Partnership with Villages for Enhanced Safety Inspections

Article Summary: The Manhattan Fire Protection District is exploring a potential intergovernmental agreement with local villages to streamline and improve fire prevention and code enforcement efforts. The collaboration would see...
Peotone fire district graphic logo.1

Manhattan Fire District Plans Major Staff Expansion, Promotions in Early 2026

Article Summary: The Manhattan Fire Protection District is planning a significant expansion of its force, with plans to hire three new full-time firefighters and promote nine current members early next...
MH VB 7.15.25

Manhattan Secures Irish Fest for Four More Years with Financial Support

The Manhattan Irish Fest, a staple event that has drawn crowds to the village for over 30 years, is officially set to continue its run for another four years. The...
WCO-PZ-July-15

Crete Township Wins Approval for New Digital Sign at Community Center

Crete Township received approval from the Will County Planning and Zoning Commission on Tuesday for a new digital sign at its community center, a project that required a special use...
MH VB 7.15.25

Manhattan to Begin Paying Emergency Management Volunteers in ‘Long Overdue’ Move

Members of Manhattan’s Emergency Management Agency (EMA), who have served for years as unpaid volunteers, will now receive financial compensation for their service. The Village Board on Tuesday unanimously approved...
WCO-PZ-July-15

Will County Planners OK Oversized Garage Near Naperville, Overriding Staff Recommendation

The Will County Planning and Zoning Commission on Tuesday approved variances for a new oversized accessory garage in Wheatland Township, siding with a homeowner and builder over a staff recommendation...
MH VB 7.15.25

Manhattan Approves 14 New Homes, Bike Path Completion in Whitefeather Subdivision

The Whitefeather subdivision is set for further expansion after the Manhattan Village Board approved the final plat for a new 14-home unit on Tuesday. The approval allows developer McDonnell Development...
WCO-PZ-July-15

Green Garden Landscaping Business Gains Permit Amid Strong Neighbor Support

A small landscaping and lawn maintenance business operating on a residential property in Green Garden Township received official approval Tuesday after neighbors voiced overwhelming support for the operation. The Will...
Meeting Briefs

Meeting Briefs: Will County Planning and Zoning Commission for July 15, 2025

Frankfort Shed Relocation Approved: A homeowner on West Harvest Drive in Frankfort Township received a variance to reduce an east side-yard setback from 10 to 4 feet. The variance, sought by...
Meeting Briefs

Meeting Briefs: Manhattan Village Board for July 15, 2025

New Planning Commissioner Appointed: Mayor Mike Adrieansen appointed Gwen Petrella to the Manhattan Planning and Zoning Commission. The Village Board unanimously authorized the appointment for a term ending May 1, 2026....
manhattan fire district graphic logo.1

Manhattan Fire District Re-evaluating New Station Plans After Bids Come in Over Budget

Article Summary: Construction bids for a new Manhattan Fire Protection District station have come in over the district's maximum price, forcing officials to re-evaluate the project's scope. Chief Steve Malone...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Approves ‘Whisk & Flame’ Culinary Studio, Slashes Parking Requirement for Downtown Property

An experiential culinary studio named Whisk & Flame is set to open in downtown Frankfort after the Village Board approved a series of special use permits and a significant parking...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Village Board Adopts $59.4 Million Appropriation for Fiscal Year 2026

The Frankfort Village Board has formally set its maximum legal spending limit for the upcoming fiscal year, adopting a $59,366,900 appropriation ordinance for fiscal year 2026. The measure was passed...
Frankfort-Village-Board-Meeting-Graphic

Frankfort Establishes New Zoning Rules to Attract Data Centers

The Village of Frankfort has amended its zoning ordinance to create a specific use category for data centers, a move designed to regulate and attract high-tech development. The Village Board...