Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township

Spread the love

Article Summary: The Forest Preserve District is currently undertaking dual construction projects on the Plum Creek Greenway Trail, initiating a massive 1.5-mile southern extension through Plum Valley Preserve and commencing repairs on an 80-foot bridge damaged by a fallen tree in Goodenow Grove Nature Preserve.

Plum Creek Greenway Trail Projects Key Points:

  • A new 1.5-mile trail extension will connect Plum Valley Preserve to Goodenow Grove Nature Preserve in Crete Township, with an estimated completion date of fall 2026.

  • The extension features the installation of 800 feet of elevated concrete boardwalks and a 150-foot bridge over Plum Creek, which will become the District’s largest single-span bridge.

  • Repairs began in early March on an 80-foot bridge in Goodenow Grove that was heavily damaged by a fallen tree in January 2025. Contractors are installing new footings, supports, and decking.

  • Future phases of the trail extension aim to connect the path north into Cook County and south to Beecher via the proposed Vincennes Trail.

  • The projects are locally funded by the Forest Preserve District’s Capital Improvement Program and a 2024–2028 grant from the Chicago Metropolitan Agency for Planning.

The Forest Preserve District announced in early March that dual construction projects are currently underway to expand and repair the Plum Creek Greenway Trail, promising significant upgrades for outdoor recreation in Crete Township and the surrounding Will County communities.

The most expansive of the two projects is a new 1.5-mile trail extension that will head south, winding through a hilly section of Plum Valley Preserve. The new multi-use trail will feature a 10-foot-wide path with 3-foot turf shoulders on each side. The extension will consist of a half-mile of crushed limestone, a half-mile of asphalt, and a half-mile street route.

The short street connection will be marked with explicit street signs and pavement directions, leading path users from the newly built trail section to an existing 3.15-mile leg of the Plum Creek Greenway Trail at Goodenow Grove Nature Preserve. The new construction is being added to an existing 1-mile crushed limestone segment that extends south from the Plum Valley Preserve entrance and dog park.

“Upon completion, the project will eliminate a gap in the existing trail system, resulting in a continuous greenway trail connection between Goodenow Grove Nature Preserve and the Plum Valley Preserve – Burville Road access,” said Colleen Novander, the Forest Preserve District’s director of planning and land preservation.

To navigate sensitive ecological areas, contractors are actively installing sections of a precast concrete pedestrian boardwalk to elevate the path. Crews will lay down one 600-foot section and another 200-foot section of boardwalk, utilizing massive concrete components that weigh 4,000 pounds each.

Additionally, concrete abutments are being poured and cured to support a new bridge spanning Plum Creek. Expected to be installed later in April, the 150-foot structure will be the largest single-span bridge in the District.

To minimize environmental impact to existing natural features like wetlands, ravines, and sensitive habitats, the engineering phase dictated that construction remain confined to a designated corridor with a maximum width of 100 feet.

The extension project, which carries an estimated completion date of fall 2026, is funded by the Forest Preserve District’s Capital Improvement Program. Supplemental funding support is provided through the Chicago Metropolitan Agency for Planning’s (CMAP) 2024–2028 Locally Programmed Transportation Alternatives Program (TAP-L).

Looking ahead, District officials noted that future phases of the trail will provide a critical north–south connection, eventually extending the path north into Cook County and south to the Village of Beecher via the proposed Vincennes Trail.

Goodenow Grove Bridge Repairs
While the extension moves forward, a separate set of contractors began repair work in early March on an existing bridge located in the eastern section of Goodenow Grove Nature Preserve, near East Bemes Road.

The 80-foot bridge, which sits just north of the preserve’s well-known “big bridge,” was significantly damaged in January 2025 when a large tree fell on the structure. Following the incident, the District consulted engineers to determine if the bridge required a total replacement or if it could be salvaged. Engineers ultimately concluded that the structure could be repaired.

Originally built in 2011 in tandem with the initial construction of the Plum Creek Greenway Trail and a capital redesign project at Goodenow Grove, the bridge requires extensive rehabilitation. Contractors are currently replacing one of the bridge’s main support structures and pouring new concrete footings. Additionally, all of the bridge’s decking and railings will be entirely replaced.

“It will look like a brand new bridge,” stated Chris Moeller, a Forest Preserve operations department supervisor.

The section of the Plum Creek Greenway Trail affected by the damage has been closed to the public since the tree fell in January. District officials anticipate the repairs will take several weeks to complete, noting that weather and other factors could impact the timeline. The trail segment will officially reopen once the reconstruction is finalized.

—Photo by Glenn P. Knoblock

Leave a Comment





Latest News Stories

lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
District 114 Graphic

Manhattan School District 114 Approves $41.5 Million Budget for FY26

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a fiscal year 2026 budget with $41.5 million in expenditures, a figure significantly influenced by the final costs...
Peotone fire district graphic logo.1

Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings

Article Summary: The Manhattan Fire Protection District is moving forward with plans for a new Station 81 after holding a public hearing for an $8.75 million bond sale and approving...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...