Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township

Spread the love

Article Summary: The Forest Preserve District is currently undertaking dual construction projects on the Plum Creek Greenway Trail, initiating a massive 1.5-mile southern extension through Plum Valley Preserve and commencing repairs on an 80-foot bridge damaged by a fallen tree in Goodenow Grove Nature Preserve.

Plum Creek Greenway Trail Projects Key Points:

  • A new 1.5-mile trail extension will connect Plum Valley Preserve to Goodenow Grove Nature Preserve in Crete Township, with an estimated completion date of fall 2026.

  • The extension features the installation of 800 feet of elevated concrete boardwalks and a 150-foot bridge over Plum Creek, which will become the District’s largest single-span bridge.

  • Repairs began in early March on an 80-foot bridge in Goodenow Grove that was heavily damaged by a fallen tree in January 2025. Contractors are installing new footings, supports, and decking.

  • Future phases of the trail extension aim to connect the path north into Cook County and south to Beecher via the proposed Vincennes Trail.

  • The projects are locally funded by the Forest Preserve District’s Capital Improvement Program and a 2024–2028 grant from the Chicago Metropolitan Agency for Planning.

The Forest Preserve District announced in early March that dual construction projects are currently underway to expand and repair the Plum Creek Greenway Trail, promising significant upgrades for outdoor recreation in Crete Township and the surrounding Will County communities.

The most expansive of the two projects is a new 1.5-mile trail extension that will head south, winding through a hilly section of Plum Valley Preserve. The new multi-use trail will feature a 10-foot-wide path with 3-foot turf shoulders on each side. The extension will consist of a half-mile of crushed limestone, a half-mile of asphalt, and a half-mile street route.

The short street connection will be marked with explicit street signs and pavement directions, leading path users from the newly built trail section to an existing 3.15-mile leg of the Plum Creek Greenway Trail at Goodenow Grove Nature Preserve. The new construction is being added to an existing 1-mile crushed limestone segment that extends south from the Plum Valley Preserve entrance and dog park.

“Upon completion, the project will eliminate a gap in the existing trail system, resulting in a continuous greenway trail connection between Goodenow Grove Nature Preserve and the Plum Valley Preserve – Burville Road access,” said Colleen Novander, the Forest Preserve District’s director of planning and land preservation.

To navigate sensitive ecological areas, contractors are actively installing sections of a precast concrete pedestrian boardwalk to elevate the path. Crews will lay down one 600-foot section and another 200-foot section of boardwalk, utilizing massive concrete components that weigh 4,000 pounds each.

Additionally, concrete abutments are being poured and cured to support a new bridge spanning Plum Creek. Expected to be installed later in April, the 150-foot structure will be the largest single-span bridge in the District.

To minimize environmental impact to existing natural features like wetlands, ravines, and sensitive habitats, the engineering phase dictated that construction remain confined to a designated corridor with a maximum width of 100 feet.

The extension project, which carries an estimated completion date of fall 2026, is funded by the Forest Preserve District’s Capital Improvement Program. Supplemental funding support is provided through the Chicago Metropolitan Agency for Planning’s (CMAP) 2024–2028 Locally Programmed Transportation Alternatives Program (TAP-L).

Looking ahead, District officials noted that future phases of the trail will provide a critical north–south connection, eventually extending the path north into Cook County and south to the Village of Beecher via the proposed Vincennes Trail.

Goodenow Grove Bridge Repairs
While the extension moves forward, a separate set of contractors began repair work in early March on an existing bridge located in the eastern section of Goodenow Grove Nature Preserve, near East Bemes Road.

The 80-foot bridge, which sits just north of the preserve’s well-known “big bridge,” was significantly damaged in January 2025 when a large tree fell on the structure. Following the incident, the District consulted engineers to determine if the bridge required a total replacement or if it could be salvaged. Engineers ultimately concluded that the structure could be repaired.

Originally built in 2011 in tandem with the initial construction of the Plum Creek Greenway Trail and a capital redesign project at Goodenow Grove, the bridge requires extensive rehabilitation. Contractors are currently replacing one of the bridge’s main support structures and pouring new concrete footings. Additionally, all of the bridge’s decking and railings will be entirely replaced.

“It will look like a brand new bridge,” stated Chris Moeller, a Forest Preserve operations department supervisor.

The section of the Plum Creek Greenway Trail affected by the damage has been closed to the public since the tree fell in January. District officials anticipate the repairs will take several weeks to complete, noting that weather and other factors could impact the timeline. The trail segment will officially reopen once the reconstruction is finalized.

—Photo by Glenn P. Knoblock

Leave a Comment





Latest News Stories

Screenshot 2026-02-22 at 5.06.42 PM

Trustees Renew Federal Lobbyist Contract Following $800,000 Funding Win

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board voted to renew its contract for federal lobbyist services on Wednesday. Administration and supporting...
Committee-Executive.Graphic

Executive Committee Advances $28.7 Million BNSF Bridge Project for Lorenzo Road

Will County Executive Committee Meeting | February 11, 2026 Article Summary: The Executive Committee approved an agreement with BNSF Railway to construct a grade separation bridge on Lorenzo Road in...
manhattan elwood library graphic.4

Meeting Summary and Briefs: Manhattan-Elwood Public Library District for January 26, 2026

Manhattan-Elwood Public Library District Meeting | January 26, 2026 The Manhattan-Elwood Public Library District Board of Trustees held a highly productive, 52-minute regular meeting on Monday afternoon to authorize capital...
Committee-Land Use.Graphic

Land Use Committee: ‘Clean Fill’ Proposal Stalls After Unauthorized Tree Removal Sparks Environmental Concerns

Will County Land Use & Development Committee Meeting | February 5, 2026 Article Summary: A request to rezone land for a "clean fill" operation in Joliet Township stalled in committee...
Screenshot 2026-03-22 at 12.12.19 PM

Manhattan School District Approves Tax Abatement and Fund Transfers

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: The Manhattan School District 114 Board of Education unanimously approved two key financial resolutions to transfer operational funds and...
Screenshot 2026-02-22 at 4.29.56 PM

Contracts Approved for New West Principal and District Technology Director

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board appointed Dr. Jennifer Killeen as the new Principal of Lincoln-Way West High School and Kyle...
manhattan elwood library graphic.2

Manhattan-Elwood Library Officially Adopts “Library of Things” Policies and Patron Waivers

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: Patrons will soon have new non-traditional borrowing options after the library board formally adopted policies and liability waivers to govern...
Committee-Planning & Zoning.Graphic

Meeting Summary and Briefs: Will County Planning and Zoning Commission for February 17, 2026

Will County Planning and Zoning Commission Meeting | February 17, 2026 JOLIET, IL – The Will County Planning and Zoning Commission met on Tuesday, February 17, 2026, with Acting Chairman John...
Committee-Ad-Hoc.Graphic

Ad-Hoc Committee: Liquor Ordinance Stalls Over Drafting Errors; Debates License Cap Policy

Will County Ad-Hoc Ordinance Review Committee Meeting | February 10, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee postponed a vote on the comprehensive update to the...
Screenshot 2026-02-22 at 5.06.42 PM

Board Approves New Chief of Staff and Dean Roles; Trustees Clash Over Hiring Transparency

Joliet Junior College Board of Trustees Meeting | February 18, 2026 Article Summary: The JJC Board approved the appointments of a new Chief of Staff and a Dean of Workforce...
Committee-Executive.Graphic

Green Garden Township Residents Threaten Incorporation to Block 6,000-Acre Solar Farm

Will County Executive Committee Meeting | February 11, 2026 Article Summary: Residents of Green Garden Township warned county officials they are moving to incorporate as a village to gain zoning...
manhattan elwood library graphic.5

Library Board Proposes Land-for-Services Swap with Village of Elwood for Mississippi Lot

Manhattan-Elwood Public Library District Meeting | January 26, 2026 Article Summary: The Manhattan-Elwood Public Library District Board voted to offer a piece of property to the Village of Elwood in exchange...
Jackson Township Graphic.1 NEW

Meeting Summary and Briefs: Jackson Township Board for January 14, 2026

Jackson Township Board Meeting | January 14, 2026 The Jackson Township Board of Trustees met for its regular monthly meeting on January 14, 2026, at the Jackson Township Hall. Supervisor...
Screenshot 2026-03-22 at 12.12.19 PM

Winter Benchmark Data Highlights Growth in Reading and Math Across Manhattan District 114

Manhattan School District 114 Meeting | February 11, 2026 Article Summary: Manhattan School District 114 administrators presented winter benchmark data showing strong academic growth across all grade levels, with significant...
Screenshot 2026-02-22 at 4.29.56 PM

Board Approves $479,000 Wireless Network Overhaul to Replace Aging Tech

Lincoln-Way District 210 Board of Education Meeting | February 19, 2026 Article Summary: The Board of Education approved a $479,526.96 contract with CDW to replace the indoor wireless access points...