Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Leave a Comment





Latest News Stories

WATCH: New survey finds more WA businesses considering moving out of state

By Carleen JohnsonThe Center Square A new survey of Washington businesses reveals growing pessimism about the state’s economy and ability to be successful in the Evergreen state. The survey conducted...
Minnesota committee fails to subpoena Omar after unanswered records request

Minnesota committee fails to subpoena Omar after unanswered records request

By Elyse ApelThe Center Square Democrats on a Minnesota House committee refused to support a subpoena targeting U.S. Rep. Ilhan Omar after Republicans accused her of ignoring repeated requests for...
Minnesota committee fails to subpoena Omar after unanswered records request

Minnesota committee fails to subpoena Omar after unanswered records request

By Elyse ApelThe Center Square Democrats on a Minnesota House committee refused to support a subpoena targeting U.S. Rep. Ilhan Omar after Republicans accused her of ignoring repeated requests for...
Illinois Quick Hits: State police investigating 2025 fatal ICE-involved shooting

Illinois Quick Hits: State police investigating 2025 fatal ICE-involved shooting

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Illinois State Police have begun investigating the fatal shooting of Silverio Villegas Gonzalez last September by a...
Data shows more violent retail thefts, lost sales tax revenue.

Data shows more violent retail thefts, lost sales tax revenue.

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – New data shows that violent retail crime is on the rise, and taxpayers can be counted among...
Data shows more violent retail thefts, lost sales tax revenue.

Data shows more violent retail thefts, lost sales tax revenue.

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – New data shows that violent retail crime is on the rise, and taxpayers can be counted among...
Arizona GOP considers suing to redraw congressional map

Arizona GOP considers suing to redraw congressional map

By Zachery SchmidtThe Center Square The Republican majority in the Arizona Legislature is contemplating legal options to redraw the state’s congressional map in time for the 2028 elections. Senate President...
Arizona GOP considers suing to redraw congressional map

Arizona GOP considers suing to redraw congressional map

By Zachery SchmidtThe Center Square The Republican majority in the Arizona Legislature is contemplating legal options to redraw the state’s congressional map in time for the 2028 elections. Senate President...
Arizona GOP considers suing to redraw congressional map

Arizona GOP considers suing to redraw congressional map

By Zachery SchmidtThe Center Square The Republican majority in the Arizona Legislature is contemplating legal options to redraw the state’s congressional map in time for the 2028 elections. Senate President...
Illinois Quick Hits: Congressman's aide indicted on fraud allegations

Illinois Quick Hits: Congressman’s aide indicted on fraud allegations

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – U.S. Rep. Danny Davis’ deputy director has been indicted on federal fraud charges. Prosecutors say Gerard C....
Screenshot 2026-05-05 at 1.46.14 PM

JJC Board Meeting Halted by Lack of Quorum; New Student Trustee Sworn In

Joliet Junior College Board of Trustees Meeting | April 15, 2026 Article Summary: A lack of a voting quorum forced the Joliet Junior College Board of Trustees to delay all official...
jackson township graphic.2

Jackson Township Outlines Spring Community Outreach, Prepares for Route 66 Centennial

Jackson Township Board Meeting | March 11, 2026 Article Summary: Jackson Township officials announced a robust schedule of spring community initiatives, highlighted by an expanded food basket distribution program and early...
Johnson, municipal leaders statewide clash with Pritzker over local funding cuts

Johnson, municipal leaders statewide clash with Pritzker over local funding cuts

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Mayors and municipalities across Illinois have called on Gov. JB Pritzker to reverse course on local government...
Johnson, municipal leaders statewide clash with Pritzker over local funding cuts

Johnson, municipal leaders statewide clash with Pritzker over local funding cuts

By Sean Reed | The Center SquareThe Center Square (The Center Square) – Mayors and municipalities across Illinois have called on Gov. JB Pritzker to reverse course on local government...
Lincoln Way West Warriors Baseball

Pettit’s Home Run, Late Rally Propel Lincoln-Way West Baseball Past Andrew 5-2

Overcoming a mid-game deficit with a clutch late-inning surge, the Lincoln-Way West varsity baseball team secured a hard-fought 5-2 conference victory over host Andrew on Tuesday afternoon. Trailing 2-1 entering...