Manhattan School Board Approves Summer Roofing Contract, Prepares for Lighting and HVAC Upgrades

Spread the love

Manhattan School District 114 Board of Education Meeting | April 29, 2026

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a summer roofing repair contract for three of its school buildings and outlined an extensive capital projects schedule. The work includes roofing, seal coating, Phase 2 LED lighting upgrades, and preparation for a major HVAC overhaul at Anna McDonald and Manhattan Intermediate School.

Capital Projects Key Points:

  • Roofing repairs will span from June 9 to August 12 across Wilson Creek, Anna McDonald, and MIS.

  • The district added a $50,000 to $60,000 shingle replacement at Wilson Creek based on architectural audits.

  • The modular classrooms at Wilson Creek will be removed the week of June 20.

  • A $19,000 seal coating project is slated for Wilson Creek in late July.

The Manhattan School District 114 Board of Education on Tuesday, April 29, 2026, unanimously approved an independent contractor agreement to execute comprehensive roof repairs across Wilson Creek Elementary, Anna McDonald School, and Manhattan Intermediate School (MIS).

The roofing project, coordinated between STR Partners and Anthony Roofing, is scheduled to commence on June 9, the first week after students are dismissed for the summer. Crews will start at Wilson Creek, move to Anna McDonald, and finish at MIS, dedicating roughly three to four weeks to each building. The target completion date is August 12, roughly a week before the new school year begins.

Administrators confirmed that the approved contract includes an added scope of work for Wilson Creek. Based on a 10-year facility audit conducted by STR, the district opted to replace the building’s shingles for an estimated $50,000 to $60,000 while crews are already mobilized on-site.

“Considering we’re doing everything else, it would be kind of silly to come back and do that,” Board President John Burke said before the 5-0 roll call vote.

The roofing contract is just one piece of a packed summer capital improvement schedule. District facilities staff updated the Board on several imminent upgrades, including a $19,000 seal coating project at Wilson Creek scheduled for the week of July 20, which will require subsequent Board approval due to the bidding threshold.

Inside Wilson Creek, district custodians are currently working to paint classrooms for the first time in 20 years. Priority is being given to the rooms designated for the Preschool for All (PFA) program. The PFA classes will be moving out of the temporary modular classrooms, which are scheduled to be physically removed from the campus the week of June 20.

The Board also reviewed plans to stagger Phase 2 of the district’s lighting upgrades to avoid triggering legal bidding thresholds. The district plans to approve lighting for MIS in May, Anna McDonald in June, and break Wilson Creek’s lighting into two parts spanning July and August. Administrators noted Phase 3 will likely target the district’s dim bathroom spaces.

Looking ahead, the district is preparing for its most expensive upcoming capital project: a full HVAC replacement at Anna McDonald and MIS. STR Partners and 2010 Engineering are currently developing the scope of work based on a recent facility walkthrough.

When Board Member Erica Aultz asked what season HVAC repairs generally occur, staff confirmed the work is strictly relegated to the summer months due to the highly intrusive nature of ripping out unit ventilators and potentially updating the boiler systems. The district expects to put the HVAC project out to bid in the fall to lock in pricing for next year.

Leave a Comment





Latest News Stories

lincoln way school district 210 logo.1

Lincoln-Way 210 to Launch District Literacy Plan, Expands Community Partnerships

Article Summary: As part of its strategic plan, Lincoln-Way High School District 210 is developing a comprehensive literacy plan to embed critical thinking skills across the curriculum. The district is also...
Meeting Briefs

Meeting Summary and Briefs: Manhattan School District 114 Board of Education for September 17, 2025

The Manhattan School District 114 Board of Education heard emotional testimony from parents regarding serious transportation safety and timeliness issues at its Wednesday meeting. The board also formally approved the...
jackson township graphic.2

Jackson Township Refers Manure-to-Gas Plant Proposal to Planning Commission

Article Summary: Representatives for a company named Elwood81, LLC, presented a proposal for an anaerobic digestion facility to the Jackson Township Board. Following the presentation, the board directed the company...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Manhattan School District 114 Logo Graphic

School Board Approves ‘Board Book Premier’ for Paperless Meetings

Article Summary: The Manhattan School District 114 will transition to a digital platform for its board meetings, selecting Board Book Premier to improve public access to documents and create a...
Screenshot

Lincoln-Way 210 Prepares for “Retirement Wave” with Focus on Recruitment

Article Summary: Lincoln-Way High School District 210 is bracing for a significant number of retirements, with 47 teachers expected to leave over the next four years, representing nearly a quarter of...
Press Plus

District 114 to Overhaul Policy Updates with New ‘Press Plus’ Service

Article Summary: Manhattan School District 114 is moving forward with Press Plus, a service from the Illinois Association of School Boards designed to streamline and modernize the updating of its...
lincoln way school district 210 logo.2

Lincoln-Way Board Weighs Community Solar Program Promising $155,000 in Annual Savings

Article Summary: The Lincoln-Way District 210 board is considering a 20-year agreement to participate in a state-sponsored community solar program that could save the district an estimated $155,000 annually on electricity...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Meeting Briefs

Meeting Summary and Briefs: Joliet Junior College Board of Trustees for September 10, 2025

Joliet Junior College Board of Trustees Meeting | September 2025 The Joliet Junior College (JJC) Board of Trustees approved a landmark agreement with the City of Joliet to explore a...
manhattan park district graphic.2

Manhattan Park Board Hires New Architect for Round Barn Buildout, Secures Annexation for Future Banquet Hall

Article Summary: The Manhattan Park Board advanced its plans for the historic Round Barn Farm on Thursday, August 14, 2025, by hiring a new design firm for a partial interior...
Screenshot

Lincoln-Way 210 Board Approves $172.7 Million Budget with Planned Deficit for Bus Purchases

Article Summary: The Lincoln-Way Community High School District 210 Board of Education approved the Fiscal Year 2026 budget, which includes a planned operating deficit of $814,000 to accommodate the purchase of...
District 114 Graphic

Manhattan School District 114 Approves $41.5 Million Budget for FY26

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a fiscal year 2026 budget with $41.5 million in expenditures, a figure significantly influenced by the final costs...
Peotone fire district graphic logo.1

Manhattan Fire District Advances New Station with $8.75M Bond Hearing, Approves Contracts with $194,000 Savings

Article Summary: The Manhattan Fire Protection District is moving forward with plans for a new Station 81 after holding a public hearing for an $8.75 million bond sale and approving...
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...