Manhattan School Board Approves Summer Roofing Contract, Prepares for Lighting and HVAC Upgrades

Spread the love

Manhattan School District 114 Board of Education Meeting | April 29, 2026

Article Summary: The Manhattan School District 114 Board of Education unanimously approved a summer roofing repair contract for three of its school buildings and outlined an extensive capital projects schedule. The work includes roofing, seal coating, Phase 2 LED lighting upgrades, and preparation for a major HVAC overhaul at Anna McDonald and Manhattan Intermediate School.

Capital Projects Key Points:

  • Roofing repairs will span from June 9 to August 12 across Wilson Creek, Anna McDonald, and MIS.

  • The district added a $50,000 to $60,000 shingle replacement at Wilson Creek based on architectural audits.

  • The modular classrooms at Wilson Creek will be removed the week of June 20.

  • A $19,000 seal coating project is slated for Wilson Creek in late July.

The Manhattan School District 114 Board of Education on Tuesday, April 29, 2026, unanimously approved an independent contractor agreement to execute comprehensive roof repairs across Wilson Creek Elementary, Anna McDonald School, and Manhattan Intermediate School (MIS).

The roofing project, coordinated between STR Partners and Anthony Roofing, is scheduled to commence on June 9, the first week after students are dismissed for the summer. Crews will start at Wilson Creek, move to Anna McDonald, and finish at MIS, dedicating roughly three to four weeks to each building. The target completion date is August 12, roughly a week before the new school year begins.

Administrators confirmed that the approved contract includes an added scope of work for Wilson Creek. Based on a 10-year facility audit conducted by STR, the district opted to replace the building’s shingles for an estimated $50,000 to $60,000 while crews are already mobilized on-site.

“Considering we’re doing everything else, it would be kind of silly to come back and do that,” Board President John Burke said before the 5-0 roll call vote.

The roofing contract is just one piece of a packed summer capital improvement schedule. District facilities staff updated the Board on several imminent upgrades, including a $19,000 seal coating project at Wilson Creek scheduled for the week of July 20, which will require subsequent Board approval due to the bidding threshold.

Inside Wilson Creek, district custodians are currently working to paint classrooms for the first time in 20 years. Priority is being given to the rooms designated for the Preschool for All (PFA) program. The PFA classes will be moving out of the temporary modular classrooms, which are scheduled to be physically removed from the campus the week of June 20.

The Board also reviewed plans to stagger Phase 2 of the district’s lighting upgrades to avoid triggering legal bidding thresholds. The district plans to approve lighting for MIS in May, Anna McDonald in June, and break Wilson Creek’s lighting into two parts spanning July and August. Administrators noted Phase 3 will likely target the district’s dim bathroom spaces.

Looking ahead, the district is preparing for its most expensive upcoming capital project: a full HVAC replacement at Anna McDonald and MIS. STR Partners and 2010 Engineering are currently developing the scope of work based on a recent facility walkthrough.

When Board Member Erica Aultz asked what season HVAC repairs generally occur, staff confirmed the work is strictly relegated to the summer months due to the highly intrusive nature of ripping out unit ventilators and potentially updating the boiler systems. The district expects to put the HVAC project out to bid in the fall to lock in pricing for next year.

Leave a Comment





Latest News Stories

diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
District 114 Bus

Parents Voice Alarms Over Bus Safety, Lateness in Manhattan School District

Article Summary: Parents raised serious transportation safety and reliability concerns at the Manhattan School District 114 board meeting, including a harrowing account of a kindergartener being dropped off at the...
Meeting Briefs

Meeting Summary and Briefs: Village of Manhattan Board of Trustees for September 16, 2025

The Manhattan Village Board took steps to prepare for future growth at its Tuesday meeting, awarding a contract of over half a million dollars to extend water and sewer infrastructure...
Joliet-Junior-college.-Graphic-Logo.4

Joliet Junior College Honors Seven Long-Serving Employees Upon Retirement

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College Board of Trustees formally recognized seven long-serving employees who are retiring, including Dr. Robert "Bob"...
Screenshot 2025-09-27 at 8.39.48 AM

Manhattan Police Department Promotes Garrison to Commander, Diaz to Sergeant

Article Summary: The Manhattan Police Department solidified its command structure with the promotions of William Garrison to the rank of Commander and Bryan Diaz to Sergeant, who were both officially...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Fire Protection District for August 18, 2025

Manhattan Fire Protection District | August 18, 2025 Meeting The Manhattan Fire Protection District Board of Trustees focused on the future of its facilities and public safety at its meeting...
Screenshot 2025-09-27 at 8.36.16 AM

Village of Manhattan Honors St. Joseph’s Catholic School on its 100th Anniversary

Article Summary: The Village of Manhattan celebrated a major community milestone at its Tuesday board meeting, officially honoring St. Joseph's Catholic School for its 100th anniversary with a formal proclamation...
Joliet-Junior-college.-Graphic-Logo.4

JJC Board Approves Contract with Adjunct Faculty Union

Joliet Junior College Board of Trustees Meeting | September 2025 Article SummaryThe Joliet Junior College (JJC) Board of Trustees approved a new collective bargaining agreement with the Joliet United Adjuncts...
Screenshot 2025-09-27 at 8.36.16 AM

Manhattan Awards $547K Contract for US 52 Infrastructure Extension to Spur Growth

Article Summary: The Village of Manhattan has awarded a $547,449 contract to Speece Construction for a significant sewer and water main extension project along the US 52, Smith Road, and...
manhattan fire district graphic logo.3

Fire District to Address Safety at High-Accident Intersections with County DOT

Manhattan Fire Protection District | August 18, 2025 Meeting Article Summary: The Manhattan Fire Protection District will meet with the Will County Department of Transportation to provide data and seek...
Meeting Briefs

Meeting Summary and Briefs: Manhattan Township for August 2025

Manhattan Township Meeting | August 2025 The Manhattan Township Board took steps to address the growing interest in renewable energy at its meeting on Tuesday, August 12, 2025, by scheduling...
Screenshot 2025-09-27 at 8.16.09 AM

Manhattan Eyes Major Water and Sewer Rate Hikes to Fund Over $50 Million in Infrastructure Projects

Article Summary: To address aging infrastructure and prepare for significant future growth, Manhattan officials are planning more than $50 million in crucial water and sewer system upgrades, which will necessitate...